Plenary report, 18 December 2025

On the proposal for a regulation of the European Parliament and of the Council on the acceleration of permit-granting for defence readiness projects

Report A-10-2025-0271 · (COM(2025)0821 – C100122/2025 – 2025/0172(COD))

Committee on Security and Defence Committee on the Internal Market and Consumer Protection · Rapporteur: Lucia Yar, Henrik Dahl

On Parliament’s site PDF Word

AI: In short

Parliament's amended version of the Commission proposal for a regulation on accelerating permit-granting for defence readiness projects. It sets a 50-working-day limit for permit decisions, allows limited extensions, and requires each member state to set up a single point of contact. It defines defence readiness projects and the defence industry broadly, covering services and supply, and requires fast-track procedures, tacit approval where national law allows, and administrative support focused on SMEs and mid-caps. Member states must publish centralised online information on procedures, funding and applicable environmental, health and safety laws, and ensure impartial single points of contact with sufficient staff and digital tools. It adds rules on spatial planning, urgent dispute resolution, cross-border coordination, and annual reporting by member states to the Commission on permits, tacit approvals and SME support.

Position. The committees adopt Parliament's position at first reading with amendments to the Commission proposal, setting a 50-working-day permit limit, single points of contact, tacit approval rules, SME support and annual reporting.

Key points

  1. Defines a defence readiness project as activities, investments or measures primarily intended to enhance the defence readiness of one or several member states, including developing or modernising the defence industry.
  2. Defines the defence industry to include undertakings developing, producing, manufacturing or supplying defence-related products and those providing services that enhance member states' defence readiness.
  3. Requires each member state to establish or designate a single point of contact within 3 months of entry into force, acting as a single interface for each project.
  4. Requires the single point of contact to coordinate the permit process, give information on completeness and documentation, and allow electronic submission via a secure interoperable portal.
  5. Requires member states to give single points of contact and competent authorities enough qualified staff and financial, technical and digital resources, and lets the Commission assist with capacity building on request.
  6. Requires member states to publish centralised online information on permit procedures, funding possibilities, standardised application templates and applicable environmental, health and safety laws.
  7. Requires administrative support for all project promoters, with particular attention to SMEs and mid-caps, including compliance assistance, cross-border coordination and a dedicated SME desk.
  8. Sets the permit-granting process at no more than 50 working days from acknowledgement of completeness, with a one-time extension of up to 25 working days and a further extension of up to 50 working days in exceptional cases.
  9. Requires the single point of contact to acknowledge completeness within 12 working days, and provides that permits are deemed granted if no outcome is notified within the time limit, unless national law excludes tacit approval.
  10. Requires national, regional and local authorities to include provisions for defence readiness activities and infrastructure in spatial plans, taking account of cyber and hybrid threat security considerations.
  11. Requires dispute resolution procedures, litigation, appeals and administrative proceedings on defence readiness projects to be treated as urgent where national law provides for urgency procedures, without undermining the right to an effective remedy.
  12. Requires each member state to submit an annual statistical report to the Commission on applications, permits granted, tacit approvals and SME support, and empowers the Commission to adopt implementing acts on the reporting template.

Who is affected

  • Defence industry undertakings, including SMEs and mid-caps, which gain fast-track permits and dedicated support.
  • Member states, which must set up single points of contact, publish information and report annually.
  • National, regional and local planning authorities, which must include defence readiness provisions in spatial plans.
  • Project promoters, who can submit documents electronically and benefit from tacit approval rules.
  • The Commission, which assists with capacity building and adopts implementing acts on reporting.

Figures and deadlines

  • EUR 800bn: possible defence investment over the next four years under the ReArm Europe Plan/Readiness 2030.
  • 3 months after entry into force: deadline for member states to establish or designate a single point of contact.
  • 6 months: maximum period for a member state's time-bound plan to achieve full e-processing capability.
  • 50 working days: maximum duration of the permit-granting process from acknowledgement of completeness.
  • 25 working days: maximum one-time extension of the permit-granting time limit.
  • 50 working days: further extension in exceptional cases, decided within 25 working days of the start of the process.
  • 12 working days: deadline for the single point of contact to acknowledge completeness of an application.
  • 10 days, and not later than 3 working days: deadline for written confirmation of tacitly granted permits.

Legal basis. Article 294(2) and Article 114 of the Treaty on the Functioning of the European Union.

Written by AI from the full text · every figure comes from the text · ¶ opens the paragraph · 16 Sept 2026 · Report a problem

Full text

The Commission proposal COM(2025)0821 as published on EUR-Lex, with the 63 amendments Parliament adopted on 16 September 2026 applied; 12 could not be placed.

142 paragraphs, 51 changed, 51 amendments applied, 12 not placed

Base text: COM(2025)0821 on EUR-Lex →

deleted: Struck-through words are taken out of the proposal, inserted: marked words put in; a rule in the margin marks a changed paragraph.

Jump to a change (51)
Explanatory memorandum 48 paragraphs

EXPLANATORY MEMORANDUM

CONTEXT OF THE PROPOSAL

Reasons for and objectives of the proposal

The Russian invasion of Ukraine has underscored the need for a strengthened EU-wide market for defence products, capable of supporting the defence readiness of Member States in the face of emerging security threats. The ongoing conflict has exposed vulnerabilities in the European defence landscape, highlighting the importance of a cohesive and resilient defence industrial base. A well-functioning EU defence market is essential to ensure that Member States have access to the necessary defence capabilities, technologies and products to respond effectively to current and future security challenges.

The impact of the changing geopolitical landscape on the EU defence market has been significant, with disruptions to supply chains, increased demand for defence products and a growing need for interoperable and innovative solutions. However, existing legislation impacting the EU defence market is not adapted to the current challenges, hindering the ability of Member States to respond rapidly and effectively to emerging threats. The existing framework, developed in peacetime, is often slow to respond to the urgent needs of Member States, and fails to provide the necessary incentives for investment in defence research and development, notably to facilitate defence investments of at least EUR 800bn over the next four years, as indicated in the Joint White paper on defence readiness.

In response to these challenges, the EU must take steps to strengthen the EU-wide market for defence products, promoting a more integrated and competitive defence industrial base. By creating a more robust, resilient EU defence market and developing the necessary infrastructure the EU can support the defence readiness of Member States, promote European strategic autonomy and contribute to a more stable and secure European security environment.

This proposal is a part of the Defence Readiness Omnibus. In addition to the simplification of existing regulation contained in the other acts, this proposal sets forward the establishment of a dedicated fast-track procedure for permit granting related to defence readiness.

Consistency with existing policy provisions in the policy area

The proposal aims to adapt the provisions governing the EU-wide defence market to the current security scenario, by introducing targeted adjustments that simplify administrative procedures, cut red tape and provide more flexible solutions. By streamlining procedures and reducing bureaucratic obstacles, the proposal seeks to create a more agile and responsive EU defence market, better equipped to support the defence readiness of Member States and promote the development of a competitive and innovative European defence industry.

Consistency with other Union policies

The proposal contributes to the objectives of enhancing the EU's defence capabilities and strengthening its strategic autonomy, while also supporting the development of innovative and sustainable defence technologies. The fast-track permitting procedure established by this proposal will facilitate the rapid deployment of defence readiness projects and expected defence investments of at least EUR 800bn over the next four years, ensuring that the EU's defence industry can respond quickly to emerging security challenges and contribute to the protection of European citizens. By streamlining the permitting process, this proposal will also help to reduce administrative burdens and costs for defence companies, allowing them to focus on the delivering on the needs of the EU Member States development of cutting-edge technologies and the creation of high-skilled jobs.

The proposed measures will also contribute to the EU's resilience and strategic autonomy by ensuring the security of supply of key defence-related technologies, which is crucial for supporting the development of the EU's defence capabilities and for public order and security. By promoting the development of a strong and innovative defence industry, this proposal will help to reduce the EU's dependence on third-country suppliers and enhance its ability to respond to emerging security challenges.

The proposal is consistent with the EU policies in the fields of safety, health, environment as it does not lower standards but aims at accelerating the procedures. The proposal is without prejudice to the level of scrutiny foreseen by the applicable permit processes.

LEGAL BASIS, SUBSIDIARITY AND PROPORTIONALITY

Legal basis

The legal basis for this proposal is Article 114 TFEU. The measures proposed in this regulation have as their objective to preserve the well-functioning of the internal market, particularly the EU-wide Defence Market. In view of the current geopolitical context, the EU Member States need to rapidly increase their defence readiness. To do that, investments in defence readiness will be necessary for the functioning of the EU-wide Defence Market (such as manufacturing plants, testing facilities, as well as the necessary infrastructure.). Such development projects aimed at increasing the defence readiness of Member States or the EU require several permits to be granted. A situation in which some parts of the internal market foresee a much shorter permit-granting process would result in a serious risk to the smooth operation of the internal market. This proposal ensures that the treatment of the permit-granting process for defence readiness projects is fast and harmonized throughout the Member States.

Subsidiarity (for non-exclusive competence)

The objectives of the proposal cannot be achieved by Member States acting alone, as the problems are of a cross-border nature. The defence industry is highly integrated and interconnected, with companies operating across multiple Member States and relying on complex supply chains that transcend national borders. The proposed actions focus on areas where there is a demonstrable value added in acting at Union level due to the scale, speed and scope of the efforts needed. By establishing a fast-track permitting procedure at EU level, the proposal aims to create a level playing field for defence companies operating in the EU, ensuring that they can respond quickly and effectively ramp up defence industrial production. The EU's collective defence efforts require a coordinated approach, and the proposed mechanism will facilitate the rapid deployment of defence readiness projects.

A lack of coordination between Member States when it comes to the treatment of the permit-granting process for defence readiness projects could result in a regulatory race to the bottom or certain parts of the internal market gaining a competitive advantage. This would be undesirable as it would negatively affect the security of supply of defence products, potentially compromising the EU's ability to respond to emerging security threats. The proposed mechanism does not influence the factual basis of the granting of the permits concerned but rather establishes a single point of contact in Member States and a more agile way of dealing with permit applications. This will enable defence companies to obtain the relevant permits more efficiently, while ensuring that the necessary environmental, health and safety standards are upheld.

Proportionality

The proposal complies with the proportionality principle in that it does not go beyond the minimum required to achieve the stated objectives at the European level and which is necessary for that purpose.

In view of the unprecedented geopolitical situation, the significant threat for security of the Union and the unprecedented scale of defence in investments in the next four years, the proposed policy approach is proportionate to the scale and gravity of the problems that have been identified. The proposal is designed to strengthen the defence readiness of Member States via measures to ensure a smooth functioning the EU-wide defence market in face of the massive and urgent ramp-up of the defence production capacities.

Choice of the instrument

The Commission proposes a Regulation of the European Parliament and of the Council. This is the most suitable legal instrument as only a Regulation, with its uniform application, binding nature and direct applicability, can provide the necessary degree of uniformity needed to facilitate the deployment of defence readiness projects.

RESULTS OF EX-POST EVALUATIONS, STAKEHOLDER CONSULTATIONS AND IMPACT ASSESSMENTS

Ex-post evaluations/fitness checks of existing legislation

N/A

Stakeholder consultations

The stakeholder consultation process was comprehensive, comprising a public survey that was open until 22 April 2025, as well as a series of targeted meetings with Member States, relevant business representatives from the Union and other key stakeholders. Through this consultation process, combined with the Commission's experience in implementing the relevant legislation, key blockages and challenges within the EU regulatory environment were identified. Based on valuable input received and the Commission's expertise, the proposals outlined in this Regulation aim to address these key issues and improve the overall effectiveness of the EU regulatory framework.

Collection and use of expertise

N/A

Impact assessment

The European Council called in its Conclusions of 6 March 2025 called on the Commission to accelerate the “work on all strands to decisively ramp up Europe’s defence readiness within the next five years”. Furthermore, in the same conclusions the European Council expressly called on the Commission to rapidly follow up with simplification on security and defence.

Due to the urgent nature of the proposal, which is designed to support the rapid adaptation of the European defence industry to the new geopolitical environment and aid a country at war as of the beginning of 2023, it was not possible to deliver an impact assessment prior to the adoption of the Defence Readiness Omnibus. Within 3 months after the adoption of this proposal the Commission will present a Staff Working document to justify in detail this legislative action and explain its appropriateness to achieve the identified policy objectives in accordance with the relevant Better Regulation rules.

The proposal concerns limited and targeted changes of legislation. They are based on experience from implementing legislation. The changes do not have significant impact on the policy but only ensure a more efficient and effective implementation. Their targeted nature and the lack of relevant policy options make an impact assessment not necessary. However, the attached Communication looks at elements on the impact of such measures, including the analysis of results of an EU public survey undertaken in this context.

Regulatory fitness and simplification

The proposal to establish a single point of contact for permit-related proceedings for the defence sector, along with a fast-track permitting procedure, is expected to have a positive impact on minimizing compliance costs for SMEs, large companies and other stakeholders in the defence sector. By establishing a single point of contact in Member States, companies will no longer need to navigate multiple authorities and administrative bodies to obtain permits, reducing the time and resources spent on administrative tasks. This simplification of administrative procedures will significantly reduce uncertainty, providing defence companies with greater certainty and predictability, allowing them to plan their defence readiness activities with more confidence.

The fast-track procedure, which presumes a permit was granted if no reply is received by the set deadline, will also accelerate the permit issuance process, enabling defence companies to start their projects sooner, reducing delays and minimizing the associated costs. This streamlined process will enhance the competitiveness of the EU defence sector, particularly for SMEs, which will be able to respond more quickly to changing market conditions and customer needs. A more efficient and predictable permit issuance process will make the EU defence sector more attractive to investors, both domestic and foreign, which could lead to increased investment and growth in the sector.

This will facilitate trade in the defence sector, particularly for SMEs, which will be able to export their products and services more easily, contributing to the growth of international trade. The establishment of a single point of contact and a fast-track procedure will also facilitate cooperation between EU defence companies and their international partners, promoting the development of joint projects and collaborations, while ensuring compliance with international agreements and proportionate requirements to minimize the administrative burden on SMEs and other stakeholders.

Fundamental rights

N/A

BUDGETARY IMPLICATIONS

Upon request by a Member State, assistance for capacity-building in support of the establishment or the operation of a single contact point will be eligible for funding under the European Defence Industry Programme (EDIP) when adopted and within the agreed envelope of the programme. The capacity-building support under this proposal falls within the scope of support actions under EDIP. Due to the limited budgetary implications, no legislative financial statement will be prepared.

OTHER ELEMENTS

Implementation plans and monitoring, evaluation and reporting arrangements

N/A

Detailed explanation of the specific provisions of the proposal

This Regulation sets up streamlined permitting processes for defence readiness projects. All defence readiness projects will benefit from Member States designating a national competent authority acting as a single point of contact, in charge of coordination and facilitation of permitting, guiding economic operators, ensuring that information is publicly accessible and that all documents can be digitally submitted. The Regulation sets detailed timelines for permitting procedures. The proposal is consistent with Union legislation on permitting.

Proposal for a regulation of the European Parliament and of the Council

On the acceleration of permit-granting for defence readiness projects

THE EUROPEAN PARLIAMENT AND THE COUNCIL OF THE EUROPEAN UNION,

Having regard to the Treaty on the Functioning of the European Union, and in particular Article 114 thereof,

Having regard to the proposal from the European Commission,

After transmission of the draft legislative act to the national parliaments,

Having regard to the opinion of the European Economic and Social Committee,

Acting in accordance with the ordinary legislative procedure,

Whereas:

(1)inserted: (1) The Union is facing an acute and growing threat, as underscored in the Joint White Paper on European Defence Readiness deleted: 2030,inserted: 20302, linked to the return of full-scale conflict in deleted: Europe.inserted: Europe deleted: Ininserted: in deleted: responseinserted: the deleted: toinserted: context deleted: thisinserted: of deleted: escalatinginserted: Russia’s deleted: challenge,inserted: war deleted: itinserted: of deleted: isinserted: aggression deleted: imperativeinserted: against deleted: thatinserted: Ukraine inserted: and the deleted: Unioninserted: associated deleted: takesinserted: hybrid deleted: decisiveinserted: activities deleted: actioninserted: targeting deleted: toinserted: the deleted: bolsterinserted: Union inserted: and its deleted: defenceinserted: Member deleted: readiness.inserted: States, deleted: Thereinserted: including deleted: isinserted: sabotage, deleted: urgencyinserted: cyberattacks, deleted: toinserted: disinformation, deleted: rampinserted: economic deleted: upinserted: coercion deleted: Europeaninserted: and deleted: defenceinserted: hostile deleted: readinessinserted: intelligence deleted: toinserted: operations, deleted: ensureinserted: as deleted: thatinserted: well deleted: Europeinserted: as deleted: hasinserted: repeated deleted: ainserted: violations deleted: stronginserted: of inserted: EU and deleted: sufficientinserted: NATO deleted: Europeaninserted: airspace, deleted: defenceinserted: and deleted: postureinserted: also deleted: byinserted: an deleted: 2030inserted: evolving deleted: atinserted: transatlantic inserted: security posture. Accordingly, the deleted: latest.inserted: Union deleted: Basedinserted: must deleted: oninserted: reinforce deleted: projectionsinserted: its deleted: ofinserted: strategic deleted: gradualinserted: autonomy deleted: take-upinserted: and deleted: ofinserted: resilience. deleted: theinserted: In deleted: instrumentsinserted: response deleted: proposedinserted: to deleted: underinserted: this inserted: escalating challenge, it is imperative that the deleted: ReArminserted: Union deleted: Europeinserted: takes deleted: Plan/Readinessinserted: decisive deleted: 2030,inserted: action deleted: defenceinserted: to deleted: investmentinserted: bolster deleted: couldinserted: its deleted: reachinserted: defence deleted: atinserted: readiness deleted: leastinserted: and deleted: EURinserted: overall deleted: 800bninserted: societal deleted: overinserted: resilience, deleted: theinserted: while deleted: nextinserted: upholding deleted: fourinserted: the deleted: years.inserted: Union’s deleted: Ainserted: values deleted: crucialinserted: and deleted: aspectinserted: democratic deleted: ofinserted: principles, deleted: thisinserted: taking deleted: effortinserted: into deleted: isinserted: account the deleted: needinserted: recommendations deleted: toinserted: identified deleted: rampinserted: in deleted: upinserted: high-level deleted: theinserted: reports deleted: Union'sinserted: by deleted: defenceinserted: Mario deleted: productioninserted: Draghi, deleted: capacity,inserted: Sauli deleted: enablinginserted: Niinistö deleted: itinserted: and deleted: toinserted: Enrico deleted: respondinserted: Letta. deleted: effectivelyinserted: There inserted: is urgency to deleted: emerginginserted: ramp deleted: securityinserted: up deleted: threats.inserted: European deleted: Ininserted: defence deleted: orderinserted: readiness to deleted: achieveinserted: ensure that deleted: goal,inserted: Europe deleted: regulatoryinserted: has deleted: simplificationinserted: a inserted: strong and deleted: harmonisationinserted: sufficient deleted: areinserted: European deleted: essential.inserted: defence deleted: Byinserted: posture deleted: streamlininginserted: by deleted: andinserted: 2030 deleted: aligninginserted: at deleted: regulatoryinserted: the deleted: frameworks,inserted: latest. deleted: theinserted: It deleted: Unioninserted: is deleted: caninserted: particularly deleted: createinserted: important deleted: ainserted: to deleted: moreinserted: close deleted: conduciveinserted: the deleted: environmentinserted: most deleted: forinserted: critical deleted: defenceinserted: capability deleted: industriesinserted: shortfalls, deleted: toinserted: in deleted: operate,inserted: particular deleted: innovate,inserted: those deleted: andinserted: outlined deleted: produceinserted: in the deleted: necessaryinserted: Defence deleted: capabilitiesinserted: Readiness inserted: Roadmap 2030, ensuring that efforts to deleted: ensureinserted: close deleted: Europeaninserted: such deleted: securityinserted: shortfalls inserted: are carried out in coherence and deleted: defenceinserted: mutual deleted: readiness.inserted: reinforcement with activities carried out within NATO, while avoiding unnecessary duplications.

(1a)inserted: Based on projections of gradual take-up of the instruments proposed under the ReArm Europe Plan/Readiness 2030, defence investment could reach at least EUR 800bn over the next four years. Such a level of investment also provides an opportunity to develop the European Defence Technological and Industrial Base (EDTIB) within the single market, by enabling competitive, innovative and diverse defence technology actors to participate effectively in the EDTIB, while ensuring fair participation in the defence market, including SMEs, and in full compliance with Union and national social, labour, safety and environmental standards. A crucial aspect of this effort is the need to ramp up the Union's defence production capacity, enabling it to respond effectively to emerging security threats. In order to achieve that goal, regulatory simplification and harmonisation are essential in a way that improves efficiency, transparency, and accountability. By streamlining and aligning regulatory frameworks, the Union can create a more conducive environment for defence industries to operate, innovate, and produce the necessary capabilities to ensure European security and defence readiness. At the same time, efforts to promote a coherent approach to standardisation should be encouraged in order to strengthen interoperability and support a more efficient and coordinated development of defence capabilities across the Union.

(2)inserted: (2) In this context, defence readiness should be understood as the ability of Member States to anticipate, prevent, and respond to defence related crises, as referred to in Directive 2009/81/EC of the European Parliament and of the deleted: Councilinserted: Council3 through a proactive and coordinated approach. This includes ensuring the availability of defence industrial capacity required to acquire and maintain the necessary resources, capabilities, and infrastructure with the aim of responding effectively to such crises.inserted: Furthermore, defence readiness should also include broader preparedness, strengthening the resilience of society as a whole, to hybrid threats, disinformation campaigns, cyber attacks and other non-military forms of influence. This Regulation should apply solely to projects that contribute to the Union’s and Member States’ defence readiness and abide by the rules governing the internal market to ensure fair competition.

(3)inserted: (3) Setting up or extending facilities, infrastructure and undertaking activities related to defence readiness often requires applying for several relevant permits and approvals. Existing permitting processes for assessments across various areas are often lengthy and cumbersome. inserted: Small mid-caps and SMEs in particular are disproportionately affected, which has negative consequences for the entire supply chain. Those procedures currently lack Union-wide provisions for fast-track processes specific to defence readiness activities, which impedes the ramp-up of defence production and related infrastructure in a timely manner and defence readiness activities and investments that are crucial for meeting emerging security demands.

(4)inserted: (4) The national permit-granting process ensures that defence readiness projects are deleted: safe,inserted: carried deleted: secureinserted: out inserted: safely, securely and deleted: complyinserted: in inserted: full compliance with inserted: relevant environmental, social inserted: labour and other safety deleted: requirements.inserted: requirements inserted: throughout all stages of the process. Union environmental law sets common conditions for the content of the national permit-granting process, thereby ensuring a high level of environmental deleted: protectioninserted: protection. inserted: In light of the acute threat posed by Russia’s war of aggression against Ukraine and deleted: allowinginserted: the deleted: forinserted: accompanying inserted: hybrid activities directed against the deleted: sustainableinserted: Union deleted: exploitationinserted: and inserted: its Member States, it is essential that the application of inserted: Union and national rules enables the inserted: rapid and efficient implementation of defence readiness projects, while remaining consistent with the Union’s deleted: potentialinserted: environmental deleted: alonginserted: acquis. inserted: This approach would enable the inserted: sustainable and responsible development of Europe’s defence industrial and raw materials deleted: valueinserted: capacities, deleted: chain.inserted: while avoiding unnecessary administrative delays that could hinder security preparedness.

(5)deleted: At the same time,inserted: (5) deleted: theinserted: The unpredictability, complexity and, often, excessive length of national permit-granting deleted: processesinserted: procedures undermine deleted: the investment security inserted: certainty and planning needed for the effective strengthening of Member States defence deleted: readiness.inserted: readiness inserted: and risk discouraging innovative SMEs and small mid-caps from entering into or scaling within the defence sector. The structure and length of a permit-granting process for relevant projects can also differ greatly between Member States. Therefore, to ensure and speed up their effective implementation, Member States should apply streamlined and predictable permit-granting processes to defence readiness projects.

(5a)inserted: Defence readiness projects, including related industrial and governmental activities can, where applicable, fall within the scope of existing Union provisions allowing derogations, including from Union environmental law, on grounds of “overriding public interest”, “public safety” or “crisis” response. Member States can therefore, where so provided under national law, assess on a case-by-case basis whether permit-granting procedures for defence readiness projects can rely on those existing derogations. Any such assessment should be carried out in accordance with the conditions set out in the relevant Union and national law. Where compensatory or mitigating measures are required in the framework of the permit-granting process, they should ensure that the interests of relevant sectors are safeguarded in a proportionate manner, while preserving all obligations and safeguards laid down in the applicable legal frameworks and with a view to the timely achievement of the Defence Readiness 2030 objective.

(6)inserted: (6) While certain Member States have taken or are likely to take measures to accelerate the permission-granting processes for the defence industry, this may be done in diverging ways which would result in barriers to the functioning of the internal market in the defence sector. Divergent national legislation, regarding the planning permit-granting process of defence projects have proven to become bottlenecks for European relevant defence products supply chains. To ensure the functioning of the internal market, it is necessary to establish harmonised rules inserted: and timelines for the acceleration of the permit-granting processes.

(7)While Union institutions can provide guidance and frameworks, the responsibility for authorisation and facilitating fast-track permitting processes resides primarily with Member States. Member States are best positioned to implement changes that cater to their specific administrative and regulatory landscapes.

inserted: (7 a) The application of this Regulation should fully respect the sole responsibility of the Member States for safeguarding their national security. Essential functions, including the defence of the territory, the maintenance of law and order and the protection of public security, remain within national competence and are not affected by this Regulation. Member States can maintain or introduce extraordinary national permitting procedures, provided that such measures do not undermine the functioning of the internal market for defence readiness projects within the scope of this Regulation.

(8)inserted: (8) There is a pressing need to reduce the complexity and duration of permitting processes for defence readiness deleted: projects.inserted: projects, inserted: while ensuring that such processes are accessible to mid-caps, small mid-caps and SMEs contributing to the development of new and emerging defence technologies. By establishing national permitting frameworks that prioritise these projects and ensure their rapid processing, the Union aims to enhance its defence production capacity and readiness by 2030 at the latest.

(8a)inserted: In situations of supply chain crisis, uncertainty can hinder timely decisions and investment planning. Member States are therefore encouraged to publish and periodically update clear, accessible online information on relevant risks and bottlenecks, in line with national security and confidentiality requirements, in order to help companies anticipate and adjust their production, support the efficient allocation of scarce resources to strategically important projects and strengthen the Union’s defence industrial resilience and strategic autonomy.

(9)inserted: (9) In order to address these challenges, the defence industry should benefit of rules proven to be effective in streamlining industrial permitting deleted: processes.inserted: processes inserted: and boosting innovative defence industrial actors. Aiming to reduce permitting deadlines for defence industry activities, including construction of new plants and related infrastructure, expansion of existing facilities, establishment of testing sites, training inserted: certifying, and deleted: certifyinginserted: research inserted: and development, including prototype construction and technology transfer, while also building on and broadening existing applicable provisions.inserted: A more agile regulatory framework will free up resources for technological innovation, encourage production modularity and promote the establishment of cross-border consortia that can bridge capacity gaps more quickly.

(9a)inserted: To ensure that a streamlined permitting process and prioritisation processes cover the whole defence value chain, the concept of the defence industry should include not only undertakings manufacturing defence-related products within the meaning of Directive 2009/43/EC, but also undertakings providing services that directly enhance the defence readiness of one or more Member States. Furthermore, to address the principal bottlenecks in defence investments, the permit-granting process under this Regulation should cover all relevant permissions, including permits, approvals or licences required to build, expand, convert, operate or repurpose installations, equipment or activities for the manufacturing of defence products or components, or for other activities forming part of a defence readiness project. Bringing all such permissions into a single, coordinated and time-bound procedure, from the acknowledgement of the completeness of an application to the notification of the final decision by the single point of contact, reduces fragmentation, shortens procedural timelines and enhances legal certainty.

(10)Complying with Union law, including for instance in relation to water, waste management, air, ecosystems, habitats, archaeological, biodiversity and birds’ protection, are integral part of the permit granting procedure, also for the defence sector. Such rules are an essential safeguard to ensure negative impacts are prevented or minimised. However, to ensure that permit granting procedures for defence readiness projects are predictable and timely, any potential to streamline the required assessments and authorisations while not lowering the level of, for instance, environmental protection, should be realised. In that regard, it should be ensured that the necessary assessments are bundled to prevent unnecessary overlap.

(10a)inserted: Member States should ensure that permitting and assessment procedures required under national law are organised in a coordinated manner that complements those required under Union law, avoiding overlap, duplication and unnecessary administrative delays, while maintaining a high level of environmental protection. Where appropriate, such procedures should be coordinated or combined to provide an efficient, predictable and transparent process for project promoters.

(10b)inserted: To safeguard trust in the simplification of administrative processes, accelerated procedures and the internal market, Member States should ensure the impartiality of single points of contact and all competent national authorities involved in the permit-granting process, including through maintaining fair-competition and conflict-of-interest principles, transparency of decision-making, publication of non-confidential statistics on permit decisions. Those measures should ensure non-discriminatory access for SMEs and companies of all sizes across the Union. Member States and the Commission should ensure that appropriate measures are in place to prevent, detect, and correct any risk of fraud or corruption.

(10c)inserted: This Regulation clarifies that, when a project is subject to an environmental impact assessment pursuant to Directive 2011/92/EU, the steps (i) and (ii) of the environmental impact assessment timeline should not be included in the duration of the permit-granting process established by this Regulation. This Regulation also requires single points of contact to provide information to project promoters about the requirement to carry out an environmental impact assessment, as well as the scope and level of detail of such assessment.

(11)inserted: (11) To facilitate the efficient and timely processing of administrative permitting applications related to defence readiness activities and the scaling up of defence production, inserted: and supporting mid-caps, small mid-caps and SMEs, Member States need to ensure that the competent national authorities implement fast-track procedures. Those authorities should provide the most rapid legal treatment possible for such applications, thereby enabling timely responses to defence readiness needs.inserted: The competent authorities have flexibility to prolong the standard fast-track timeline for the reasons of potential risks to health, safety, the environment, and national security. To ensure that these exceptional circumstances are treated in rigorous and transparent manner, it is essential that competent authorities do not merely assert the existence of exceptional circumstances but substantiate such claims with verifiable evidence.

(11a)inserted: In addition, in order to further accelerate and streamline the permit issuing process, the principle of tacit approval should apply to the application for a permit except where that principle is in contradiction with the existing national legal system of a Member State. Therefore, an application for a permit should be considered granted if the project promoter has not been informed by the single point of contact within the applicable deadline of the outcome of the permit-granting process.

(11b)inserted: Where a permit for a defence readiness project is implicitly granted, such approval should not exempt the project promoter or the competent authority from full compliance with applicable Union and national law, including provisions on environmental protection and on the health and safety of workers.

(12)inserted: (12) Establishing deleted: ainserted: one inserted: or more single deleted: pointinserted: points of contact for industry applications regarding permits related to defence deleted: activitiesinserted: activities. is intended to streamline communication, inserted: clarify responsibilities, reduce administrative burdens and further expedite the permitting process with clear and legally binding deadlines, thereby providing efficient pathway for defence-related industrial applications. Moreover, it will provide certainty to investors by ensuring the rapid treatment of permit applications and limiting the risks to investments related to lengthy procedures.inserted: Member States should provide their single points of contact, as well as any authority involved in the permit-granting process, with sufficient personnel and resources.

(12a)inserted: In Member States with a federal or otherwise decentralised administrative structure, or where regional or local authorities are required to be involved in the approval process or to adopt the relevant decisions, the functions of the single point of contact may be exercised through a coordinating structure involving regional or local authorities, provided that it is ensured that project promoters have one clearly identified interface for each project, and that that interface is coordinated and streamlined. Member States should make best efforts to ensure that project promoters, in particular SMEs and small mid-caps, can easily identify and access the competent single point of contact for their specific project. Flexibility should be ensured to allow several competent authorities to operate as single points of contact where necessary, provided that clear coordination mechanisms are in place and that project promoters have one clearly identified coordinating authority acting as the sole interface for each project. Such arrangements should avoid duplication or fragmentation of procedures and preserve the efficiency and purpose of the single-point-of-contact system.

(13)To accelerate reaching full operational capacity of the single contact points Member States should, to the extent possible, take advantage of possible complementarity with existing single contact points, for example those established under Regulation (EU) 2024/1735 of the European Parliament and of the Council or Regulation (EU) 2024/1252 of the European Parliament and of the Council.

(14)inserted: (14) Furthermore, Member States should provide the necessary administrative support to defence readiness projects located on their territory, to facilitate their timely and effective implementation, paying particular attention to the needs of small and medium-sized enterprises inserted: which often face higher relative compliance costs and deleted: mid-capinserted: limited deleted: enterprisesinserted: administrative deleted: involvedinserted: capacity. deleted: ininserted: To deleted: thoseinserted: that deleted: projects,inserted: end, deleted: byinserted: the deleted: providinginserted: single deleted: assistanceinserted: point deleted: regardinginserted: of deleted: complianceinserted: contact deleted: withinserted: should deleted: applicableinserted: include deleted: administrativeinserted: dedicated inserted: support functions for SMEs and deleted: reportinginserted: midcaps, deleted: obligations,inserted: such deleted: informinginserted: as deleted: theinserted: helpdesks, deleted: publicinserted: harmonised deleted: toinserted: templates deleted: increaseinserted: and deleted: acceptanceinserted: digital deleted: ofinserted: tools, deleted: theinserted: offering deleted: projectsinserted: clear inserted: guidance on documentation and deleted: guidinginserted: compliance deleted: projectinserted: requirements deleted: promotersinserted: and deleted: throughinserted: assistance inserted: throughout the permit-granting deleted: process.inserted: process, so that smaller actors can participate effectively and without disproportionate administrative burden.

(14a)inserted: To ensure effective, transparent and comparable implementation, the performance of single points of contact should be assessed through common Union-wide indicators and data collected to be submitted by each Member State to the Commission annually.

(14b)inserted: Transparency and equal access to information are crucial for the effective implementation of permit-granting processes. Member States should ensure that all project promoters, regardless of their Member State of establishment, have support and equal access to centralised, easily accessible online information. This includes details on single points of contact, permit-granting procedures, dispute resolution mechanisms, financing and investment services, and available Union or national funding instruments.

(14c)inserted: To avoid the proliferation of uncoordinated administrative platforms, Member States should design digital tools supporting this Regulation that are interoperable in order to allow for reusing information already submitted under other Union or national procedures and offer a single, user-friendly digital interface, particularly benefiting SMEs and mid-caps.

(15)inserted: (15) The Commission deleted: mayinserted: should, inserted: upon request by a Member State offer capacity-building support to the single point of contact, including technical assistance, training, monitoring and evaluation, with the aim of developing and strengthening the abilities, processes and resources that the single points of contacts need to develop for the purposes of this Regulation. Such support may be requested by Member States and will fall within the scope of supporting actions under inserted: Regulation (EU) 20XX/XXXX on the European Defence Industry Programme [reference to be added once EDIP is adopted].

(16)In order to ensure clarity about the permitting status of defence readiness projects and to limit the effectiveness of potential abusive litigation, while not undermining effective judicial review, Member States should ensure that any dispute concerning the permit-granting process for defence readiness projects is resolved in a timely manner. To that end, Member States should ensure that project promoters have access to simple dispute settlement procedures and that defence readiness projects are subject to urgent handling in all administrative, judicial and dispute resolution procedures relating to the projects to the extent that national law provides for such urgency procedures.

(17)inserted: (17) In order to provide project promoters and other investors with the security and clarity needed to increase development of defence readiness projects, Member States should ensure that the permit-granting process related to such projects does not exceed set time limits.inserted: Completion within those time limits should take the form of a reasoned, written decision, whether granting or refusing the relevant permit, - notified by the single point of contact to the project promoter.

(18)This Regulation is without prejudice to the obligations deriving from international law, where relevant.

(19)Since the objective of this Regulation cannot be sufficiently achieved by the Member States and can rather, by reason of the scale or effects of the action, be better achieved at Union level, the Union may adopt measures in accordance with the principle of subsidiarity as set out in Article 5 of the Treaty on the European Union. In accordance with the principle of proportionality as set out in that Article, this Regulation does not go beyond what is necessary in order to achieve that objective,

HAVE ADOPTED THIS REGULATION:

Article 1 Definitions

For the purposes of this Regulation, the following definitions shall apply:

(1)inserted: (1) ‘defence readiness project’ means set of activities, investments and measures deleted: aimedinserted: or deleted: atinserted: measures deleted: enhancinginserted: primarily inserted: intended to enhance the defence readiness of a Member State or several Member States, inserted: jointly, including through the development inserted: or modernisation of the defence industry;

(2)inserted: (2) ‘defence industry’ means all undertakings engaged in the development, production, and manufacture inserted: or supply of defence-related products as defined in Article 3(1) of Directive 2009/43/EC of the European Parliament and of the Council;inserted: 6 or in the provision of services that enhance the defence readiness of one or several Member States;

(3)inserted: (3) ‘defence readiness’ means the state of preparedness of a Member State or several Member States to inserted: anticipate, prevent or respond to a crisis inserted: as defined in Article 1, point (10) of Directive 2009/81/EC of the European Parliament and of the Council, inserted: 7, which relates to defence;

(4)‘middle capitalisation company’ or ‘mid-cap’ means middle capitalisation company as defined in Article 2, point (15), of Regulation (EU) 2021/697 of the European Parliament and of the Council;

(5)‘small mid-cap enterprises’ means enterprises as defined in the Annex to Commission Recommendation (EU) 2025/1099

(6)deleted: ‘permit-grantinginserted: (6) inserted: permit-granting process’ means a process that covers all relevant inserted: permissions permits, including permits inserted: approvals or licences necessary to build, expand, convert and operate inserted: or repurpose any installation, equipment or activity for manufacturing defence deleted: readinessinserted: products deleted: projectsinserted: or deleted: andinserted: components deleted: allinserted: or deleted: theinserted: for deleted: necessaryinserted: other inserted: activities forming part of a defence readiness project together with all administrative steps from deleted: the acknowledgement deleted: that theinserted: of application deleted: is completeinserted: completeness to deleted: the notification of the final decision deleted: on that application by the single deleted: contact point deleted: concerned;inserted: of contact;

(7)‘project promoter’ means any undertaking or consortium of undertakings developing a defence readiness project;

(8)‘small and medium-sized enterprises’ or ‘SMEs’ means small and medium-sized enterprises as defined in Article 2 of the Annex to Commission Recommendation 2003/361/EC.

Article 2 Single deleted: pointinserted: points of contact

1.inserted: 1. By …[3 months after the date of entry into force of this Regulation], each Member State shall establish or designate one authority as single point of contact at the relevant administrative level.inserted: The single point of contact shall operate as a single interface for each defence readiness project.

2.inserted: 2. The single point of contact shall be responsible for facilitating and coordinating the permit-granting process for defence readiness projects and for providing information on streamlining the administrative processes in accordance with Article 3, including information to the project promoter on when an application is considered to be completed in accordance with Article 5(6).inserted: At the request of the project promoter, the single point of contact shall also provide information whether the project could be considered a defence readiness project under this Regulation, as well as information on the required documentation to be submitted as part of the final application.

3.The single point of contact established or designated pursuant to paragraph 1 shall be the sole point of contact for the project promoter in the permit-granting process for a defence readiness project. It shall notify the project promoter of the final decision in that process.

4.inserted: 4. Project promoters shall be allowed inserted: and enabled to submit any documents relevant to the permit-granting process in electronic deleted: form.inserted: form via a secure, interoperable portal. Member States shall ensure the digital exchange of documentation between the national authority, the single point of contact and the project promoters.

5.inserted: 5. The competent authorities shall ensure that any relevant studies carried out, or permits or authorisations issued, for a given project are taken into account and that no duplicate studies, permits or authorisations are required, unless otherwise required under Union or national law.inserted: The single point of contact shall ensure the coordination among the competent authorities and those authorities shall have access to all relevant documents to facilitate the fast-track procedure.

6.inserted: 6. Member States shall ensure that the single point of contact and all competent authorities responsible for any step along the permit-granting processes, including all procedural steps, have enough qualified staff and sufficient financial, technical and deleted: technologicalinserted: digital resources necessary, including, where appropriate, for up- skilling and re-skilling, for the effective performance of their tasks under this Regulation.

7.inserted: 7. The authorities involved in the permit-granting process and other authorities concerned shall specify and make available to the single point of contact concerned, the requirements and all information requested of a project promoter before the permit-granting process commences.inserted: Single points of contact shall also make available relevant and necessary documents of the project promoter to the authorities, where necessary in the permit-granting process.

8.inserted: 8. Upon request by a Member State, the Commission deleted: mayinserted: shall assist the authorities of that Member State with capacity building in support of implementation of this Regulation, notably in establishing or operating a single point of contact.inserted: The Commission shall treat that request as a priority and commence implementation without undue delay in cooperation with the requesting Member State. Such assistance may include targeted technical and financial support, such as through Regulation (EU) 20XX/XXXX on the European Defence Industry Programme and cohesion policy instruments, to help Member States with limited administrative capacity.

Article 3 Online accessibility of information

Member States shall provide public access to the following information on permit-granting processes relevant to defence readiness projects, online and in a centralised and easily accessible manner:inserted: to the extent that such publication is without prejudice to national security and with due regard to confidentiality requirements:

(a)the single points of contact referred to in Article 2(1);

(b)the permit-granting process, including information on dispute settlement concerning the permit-granting process including, where applicable, alternative dispute resolution mechanisms, if such procedures are provided for by national law;

(c)financing and investment services;

(d)inserted: (d) funding possibilities at Union deleted: orinserted: and Member State level;

(e)business support services, including but not limited to corporate tax declaration, local tax laws or labour law.

Article 4 Accelerating implementation

Member States shall provide administrative support for defence readiness projects located on their territory, inserted: to all project promoters, regardless of the Member States in which they are established, paying particular attention to SMEs and mid-caps, including small mid-cap enterprises, involved in those projects, including by providing:

(a)inserted: (a) assistance regarding compliance with applicable administrative and reporting obligations;inserted: including with Union and national health, environmental, safety, social and labour laws;

(b)assistance to project promoters to inform the public;

(c)assistance to project promoters along the permit-granting process, in particular for SMEs and small mid-cap enterprises.

Article 5 Duration of the permit-granting process

1.inserted: 1. The permit-granting process for defence readiness projects, including deleted: the grantinginserted: notification of the deleted: relevantinserted: outcome deleted: permit,inserted: of inserted: that process, shall not exceed deleted: [60]inserted: 50 deleted: days.inserted: working days from the date of the acknowledgement of the completeness of the permit-granting application by the single point of contact.

2.deleted: Whereinserted: 2. inserted: In exceptional cases, and without prejudice to the ability of the competent authorities to fully and comprehensively assess compliance with Union or national law, where a defence readiness project requires the construction of several facilities or deleted: unitsinserted: requires deleted: ininserted: several deleted: oneinserted: phases, inserted: whether located on a single site, inserted: or across multiple sites, the project promoter and the single point of contact may deleted: agreeinserted: where deleted: oninserted: justified deleted: splittinginserted: by the deleted: projectinserted: project’s deleted: intoinserted: technical deleted: severalinserted: or deleted: smallerinserted: administrative deleted: projectsinserted: characteristics, inserted: agree to process those components as separate sub-projects for the purposes of complying with the applicable time limits.

3.inserted: 3. In exceptional cases, where the nature, deleted: complexity, location or size of the proposed defence readiness project so requires, a Member State may once extend the time limits referred to in paragraph 1 by a maximum of deleted: 30inserted: 25 inserted: working days before their expiry and on a case-by-case basis.

4.inserted: 4. Where a Member State considers that inserted: there is evidence that the defence readiness project inserted: is of exceptional complexity, raises exceptional risks for the health and safety of workers or of the general population, inserted: raises an exceptional risk on the environment, or where a specific national security clearance is required, and where additional time is necessary to establish that measures to address identifiable risks have been put in place, it may extend the time limits referred to in paragraph 1 by deleted: 60inserted: 50 inserted: working days, within deleted: 30inserted: 25 inserted: working days of the start of the permit-granting process.

5.In the application of paragraph 3 or 4, the single point of contact shall inform the project promoter in writing of the reasons for the extension and of the date when the final decision is expected.

6.inserted: 6. No later than deleted: 15inserted: 12 inserted: working days from the receipt of the permit-granting application, the single point of contact concerned shall acknowledge that the application is complete and whether this Regulation applies or, if the project promoter has not sent all the information required to process the application, request the project promoter to submit a complete application without undue delay, specifying which information is missing. If the submitted application is deemed to be incomplete for a second time, the single point of contact may, within deleted: [15]inserted: 12 inserted: working days of the second submission, make a second request for information. The single point of contact shall not request information in areas not covered in the first request for information and shall be entitled only to request further evidence to complete the identified missing information.deleted: The date of the acknowledgement of the completeness of the application from the single point of contact shall serve as the start of the permit-granting process for that application.

7.The time limits set in this Article for any of the permit-granting processes shall be without prejudice to any shorter time limits set by Member States

8.inserted: 8. Where the single point of contact does not inform the project promoter of the outcome of the permit-granting process within the time limit set out in paragraph 1 and extended, where applicable, in accordance with paragraphs 3 and 4, the permits covered by the application shall be deemed to be deleted: granted.inserted: granted, inserted: unless the principle of administrative tacit approval has been excluded for these types of procedures by the national legal system of the Member state concerned. The single point of contact shall deleted: promptlyinserted: within deleted: deliverinserted: 10 inserted: days, without undue delay but not later than within 3 working days provide written confirmation to the project promoter, inserted: in writing or electronically indicating that the permits have been implicitly granted based on the application submitted.

Article 6 Planning

1.inserted: 1. National, regional and local authorities responsible for preparing plans, including zoning, spatial plans and land use plans, shall include in such plans, where appropriate, provisions for the development of defence readiness activities, projects deleted: asinserted: and deleted: wellinserted: their deleted: asinserted: required deleted: theinserted: infrastructure, deleted: necessaryinserted: and inserted: shall also take into account security considerations, including protection against cyber and hybrid threats targeting critical defence infrastructure. To facilitate the development of defence readiness projects, Member States shall ensure that deleted: allinserted: non-confidential relevant spatial planning data is available online in accordance with Article deleted: 3.inserted: 3 as well as with applicable Union and national law.

2.Where plans include provisions for the development of defence readiness projects, and their required infrastructure, and are subject to an assessment pursuant to Directive 2001/42/EC of the European Parliament and of the Council and pursuant to Article 6 of Council Directive 92/43/EEC, those assessments shall be combined. Where applicable, the combined assessment shall also address the impact on potentially affected water bodies referred to in Directive 2000/60/EC of the European Parliament and of the Council. Where relevant, the Member States are required to assess the impacts of existing and future activities on the marine environment, including land-sea interactions, as referred to in Article 4 of Directive 2014/89/EU of the European Parliament and of the Council those impacts shall also be covered in the combined assessment. The fact that assessments are combined pursuant to this paragraph shall not affect their content or quality. The combined assessment shall be carried out within the time limits set out in this Regulation.

Article 7 Priority status of defence readiness projects

All dispute resolution procedures, litigation, appeals and judicial remedies as well as all administrative proceedings related to defence readiness projects before any national courts, tribunals, bodies or panels, including with regard to mediation or arbitration, where they exist in national law, shall be treated as urgent if and to the extent to which national law concerning relevant permit-granting processes provides for such urgency procedures and provided that the applicable rights of defence of individuals or of local communities are respected. Project promoters of defence readiness projects shall participate in such urgency procedures, where applicable.inserted: The competent authorities shall guarantee that accelerated judicial and administrative procedures do not undermine the right to an effective remedy.

Article 8 Applicability of UNECE Conventions

This Regulation is without prejudice, where relevant, to the obligations under the United Nations Economic Commission for Europe (UNECE) Convention on Access to Information, Public Participation in Decision-making and Access to Justice in Environmental Matters, signed at Aarhus on 25 June 1998, and under the UNECE Convention on environmental impact assessment in a transboundary context, signed at Espoo on 25 February 1991 and its Protocol on Strategic Environmental Assessment, signed in Kyiv on 21 May 2003.

Article 9

This Regulation shall enter into force on the twentieth day following that of its publication in the Official Journal of the European Union.

It shall apply only to permit applications for defence readiness projects submitted after that date.

This Regulation shall be binding in its entirety and directly applicable in all Member States.

Not placed in the text

These amendments could not be matched to a place in the proposal, so they are not shown in it.

  • Amendment 36 · no plenary vote matched

    Placed by its location in the proposal.

    Why: location Article 2 – paragraph 4 a (new) not found in the proposal. Location: Article 2 – paragraph 4 a (new).

  • Amendment 41 · no plenary vote matched

    Placed by its location in the proposal.

    Why: location Article 2 – paragraph 8 a (new) not found in the proposal. Location: Article 2 – paragraph 8 a (new).

  • Amendment 42 · no plenary vote matched

    Placed by its location in the proposal.

    Why: location Article 2 – paragraph 8 b (new) not found in the proposal. Location: Article 2 – paragraph 8 b (new).

  • Amendment 43 · no plenary vote matched

    Placed by its location in the proposal.

    Why: location Article 2 – paragraph 8 c (new) not found in the proposal. Location: Article 2 – paragraph 8 c (new).

  • Amendment 46 · no plenary vote matched

    Placed by its location in the proposal.

    Why: location Article 3 – paragraph 1 – point e a (new) not found in the proposal. Location: Article 3 – paragraph 1 – point e a (new).

  • Amendment 47 · no plenary vote matched

    Placed by its location in the proposal.

    Why: location Article 3 – paragraph 1 – point e b (new) not found in the proposal. Location: Article 3 – paragraph 1 – point e b (new).

  • Amendment 50 · no plenary vote matched

    Placed by its location in the proposal.

    Why: location Article 4 – paragraph 1 – point c a (new) not found in the proposal. Location: Article 4 – paragraph 1 – point c a (new).

  • Amendment 51 · no plenary vote matched

    Placed by its location in the proposal.

    Why: location Article 4 – paragraph 1 – point c b (new) not found in the proposal. Location: Article 4 – paragraph 1 – point c b (new).

  • Amendment 53 · no plenary vote matched

    Placed by its location in the proposal.

    Why: location Article 5 – paragraph 1 a (new) not found in the proposal. Location: Article 5 – paragraph 1 a (new).

  • Amendment 58 · no plenary vote matched

    Placed by its location in the proposal.

    Why: location Article 5 – paragraph 6 a (new) not found in the proposal. Location: Article 5 – paragraph 6 a (new).

  • Amendment 61 · no plenary vote matched

    Placed by its location in the proposal.

    Why: location Article 6 – paragraph 2 a (new) not found in the proposal. Location: Article 6 – paragraph 2 a (new).

  • Amendment 63 · no plenary vote matched

    Placed by its location in the proposal.

    Why: location Article 8 a (new) not found in the proposal. Location: Article 8 a (new).

Parliament’s document as published (the amendments as tables) →

Procedure pages

How the committees handled the text, and how their members voted on it.

Procedure – committee asked for opinion 1 paragraph
TitleAcceleration of permit-granting for defence readiness projects
ReferencesCOM(2025)0821 – C10-0122/2025 – 2025/0172(COD)
Committee(s) responsible Date announced in plenarySEDE 8.9.2025IMCO 8.9.2025
Opinion by Date announced in plenaryENVI 8.9.2025
Rapporteur for the opinion Date appointedAntonio Decaro 1.10.2025
Rule 59 – Joint committee procedure Date announced in plenary8.9.2025
Simplified procedure - date of decision23.9.2025
Date adopted3.12.2025
Result of final vote+: –: 0:54 17 5
Members present for the final voteGrégory Allione, Pascal Arimont, Sakis Arnaoutoglou, Christophe Clergeau, Annalisa Corrado, Antonio Decaro, Viktória Ferenc, Pietro Fiocchi, Emma Fourreau, Anne-Sophie Frigout, Heléne Fritzon, Hanna Gronkiewicz-Waltz, Roman Haider, Martin Hojsík, Romana Jerković, Stefan Köhler, András Tivadar Kulja, Peter Liese, César Luena, Elżbieta Katarzyna Łukacijewska, Ignazio Roberto Marino, Dan-Ştefan Motreanu, Rasmus Nordqvist, Michele Picaro, Jessica Polfjärd, Massimiliano Salini, Silvia Sardone, Lena Schilling, Christine Schneider, Günther Sidl, Sander Smit, Susana Solís Pérez, Antonín Staněk, Ingeborg Ter Laak, Beatrice Timgren, Dimitris Tsiodras, Ana Vasconcelos, Aurelijus Veryga, Kristian Vigenin, Alexandr Vondra, Michal Wiezik, Tiemo Wölken, Anna Zalewska
Substitutes present for the final voteMichael Bloss, Biljana Borzan, Marie-Luce Brasier-Clain, Stefano Cavedagna, Susanna Ceccardi, Per Clausen, Raúl de la Hoz Quintano, Nikolas Farantouris, Sigrid Friis, Michalis Hadjipantela, Martin Häusling, Sérgio Humberto, Adam Jarubas, Pierre Jouvet, Norbert Lins, Sara Matthieu, Danuše Nerudová, Valentina Palmisano, Dennis Radtke, Elena Sancho Murillo, Antonella Sberna, Christine Singer, Anna Stürgkh, Kai Tegethoff, Ewa Zajączkowska-Hernik
Members under Rule 216(7) present for the final voteDaniel Attard, Raquel García Hermida-Van Der Walle, Mary Khan, Jaroslav Knot, Alexandra Mehnert, Matjaž Nemec, Paulius Saudargas, Volker Schnurrbusch
Final vote by roll call by the committee asked for opinion 3 paragraphs

54 · For

EPP
Pascal Arimont, Raúl de la Hoz Quintano, Hanna Gronkiewicz-Waltz, Michalis Hadjipantela, Sérgio Humberto, Adam Jarubas, Stefan Köhler, András Tivadar Kulja, Peter Liese, Norbert Lins, Elżbieta Katarzyna Łukacijewska, Alexandra Mehnert, Dan-Ştefan Motreanu, Danuše Nerudová, Jessica Polfjärd, Dennis Radtke, Paulius Saudargas, Christine Schneider, Sander Smit, Susana Solís Pérez, Ingeborg Ter Laak, Dimitris Tsiodras
Patriots
Jaroslav Knot, Antonín Staněk
Renew
Grégory Allione, Sigrid Friis, Raquel García Hermida-Van Der Walle, Martin Hojsík, Christine Singer, Anna Stürgkh, Ana Vasconcelos, Michal Wiezik
S&D
Sakis Arnaoutoglou, Daniel Attard, Biljana Borzan, Christophe Clergeau, Annalisa Corrado, Antonio Decaro, Heléne Fritzon, Romana Jerković, Pierre Jouvet, César Luena, Matjaž Nemec, Elena Sancho Murillo, Günther Sidl, Kristian Vigenin, Tiemo Wölken
Greens
Michael Bloss, Martin Häusling, Ignazio Roberto Marino, Sara Matthieu, Rasmus Nordqvist, Lena Schilling, Kai Tegethoff

17 · Against

ECR
Stefano Cavedagna, Pietro Fiocchi, Michele Picaro, Antonella Sberna, Beatrice Timgren, Aurelijus Veryga, Alexandr Vondra, Anna Zalewska
ESN
Mary Khan, Volker Schnurrbusch
Patriots
Susanna Ceccardi, Roman Haider, Silvia Sardone
The Left
Per Clausen, Nikolas Farantouris, Emma Fourreau, Valentina Palmisano

5 · Abstained

ESN
Ewa Zajączkowska-Hernik
EPP
Massimiliano Salini
Patriots
Marie-Luce Brasier-Clain, Viktória Ferenc, Anne-Sophie Frigout
Procedure – committee responsible 1 paragraph
TitleAcceleration of permit-granting for defence readiness projects
ReferencesCOM(2025)0821 – C10-0122/2025 – 2025/0172(COD)
Date submitted to Parliament18.6.2025
Committee(s) responsible Date announced in plenarySEDE 8.9.2025IMCO 8.9.2025
Committees asked for opinions Date announced in plenaryENVI 8.9.2025ITRE 8.9.2025
Not delivering opinions Date of decisionITRE 23.9.2025
Rapporteurs Date appointedLucia Yar 3.9.2025Henrik Dahl 3.9.2025
Rule 59 – Joint committee procedure Date announced in plenary8.9.2025
Discussed in committee10.11.2025
Date adopted15.12.2025
Result of final vote+: –: 0:62 6 11
Members present for the final votePeter Agius, Pablo Arias Echeverría, Petras Auštrevičius, Jeannette Baljeu, Katarina Barley, Arno Bausemer, Biljana Borzan, Marc Botenga, Stefano Cavedagna, David Cormand, Tobias Cremer, Henrik Dahl, Salvatore De Meo, Adnan Dibrani, Elisabeth Dieringer, Elio Di Rupo, Regina Doherty, Christian Doleschal, Klara Dostalova, Michał Dworczyk, Kamila Gasiuk-Pihowicz, Raphaël Glucksmann, Christophe Gomart, Sandro Gozi, Maria Grapini, Maria Guzenina, György Hölvényi, Arba Kokalari, Katrin Langensiepen, Nathalie Loiseau, Javi López, Pierfrancesco Maran, Costas Mavrides, Vangelis Meimarakis, Ana Catarina Mendes, Sven Mikser, Nikola Minchev, Piotr Müller, Denis Nesci, Hans Neuhoff, Hannah Neumann, Cynthia Ní Mhurchú, Andrey Novakov, Kostas Papadakis, Nicolás Pascual de la Parte, Jaroslava Pokorná Jermanová, Reinis Pozņaks, Marjan Šarec, Christel Schaldemose, Tomislav Sokol, Mārtiņš Staķis, Marie-Agnes Strack-Zimmermann, Michał Szczerba, Riho Terras, Pierre-Romain Thionnet, Pekka Toveri, Dimitris Tsiodras, Adina Vălean, Reinier Van Lanschot, Roberto Vannacci, Kim Van Sparrentak, Alexandr Vondra, Lucia Yar
Substitutes present for the final voteJosé Cepeda, Gheorghe Falcă, Michael Gahler, Rasa Juknevičienė, Alice Kuhnke, Gaetano Pedulla’, Hélder Sousa Silva, Matej Tonin, Kristian Vigenin, Tomáš Zdechovský
Members under Rule 216(7) present for the final voteDan Barna, Alexander Jungbluth, Moritz Körner, Lukas Mandl, Maria Noichl, Annamária Vicsek
Date tabled18.12.2025
Final vote by roll call by the committee responsible 3 paragraphs

62 · For

ECR
Stefano Cavedagna, Michał Dworczyk, Piotr Müller, Denis Nesci, Reinis Pozņaks, Alexandr Vondra
EPP
Peter Agius, Pablo Arias Echeverría, Henrik Dahl, Salvatore De Meo, Regina Doherty, Christian Doleschal, Gheorghe Falcă, Michael Gahler, Kamila Gasiuk-Pihowicz, Christophe Gomart, Rasa Juknevičienė, Arba Kokalari, Lukas Mandl, Vangelis Meimarakis, Andrey Novakov, Nicolás Pascual de la Parte, Tomislav Sokol, Hélder Sousa Silva, Michał Szczerba, Riho Terras, Matej Tonin, Pekka Toveri, Dimitris Tsiodras, Adina Vălean, Tomáš Zdechovský
Patriots
Klara Dostalova, Jaroslava Pokorná Jermanová, Pierre-Romain Thionnet
Renew
Petras Auštrevičius, Jeannette Baljeu, Dan Barna, Sandro Gozi, Moritz Körner, Nathalie Loiseau, Nikola Minchev, Cynthia Ní Mhurchú, Marjan Šarec, Marie-Agnes Strack-Zimmermann, Lucia Yar
S&D
Katarina Barley, Biljana Borzan, José Cepeda, Tobias Cremer, Adnan Dibrani, Elio Di Rupo, Raphaël Glucksmann, Maria Grapini, Maria Guzenina, Javi López, Pierfrancesco Maran, Costas Mavrides, Ana Catarina Mendes, Sven Mikser, Maria Noichl, Christel Schaldemose, Kristian Vigenin

6 · Against

ESN
Arno Bausemer, Alexander Jungbluth, Hans Neuhoff
No group
Kostas Papadakis
The Left
Marc Botenga, Gaetano Pedulla'

11 · Abstained

Patriots
Elisabeth Dieringer, György Hölvényi, Roberto Vannacci, Annamária Vicsek
Greens
David Cormand, Alice Kuhnke, Katrin Langensiepen, Hannah Neumann, Mārtiņš Staķis, Reinier Van Lanschot, Kim Van Sparrentak