Bericht, 18. Dezember 2025
On the proposal for a regulation of the European Parliament and of the Council on the acceleration of permit-granting for defence readiness projects
Bericht A-10-2025-0271 · (COM(2025)0821 – C100122/2025 – 2025/0172(COD))
Committee on Security and Defence Committee on the Internal Market and Consumer Protection · Berichterstattung: Lucia Yar, Henrik Dahl
- Abgestimmt am Mittwoch, 16. September 2026 · Angenommen 540 dafür, 105 dagegen, 22 enthalten · Zur Entscheidung →
- Stand des Verfahrens · Dossier 2025/0172 →
KI: In Kürze
Parliament's amended version of the Commission proposal for a regulation on accelerating permit-granting for defence readiness projects. It sets a 50-working-day limit for permit decisions, allows limited extensions, and requires each member state to set up a single point of contact. It defines defence readiness projects and the defence industry broadly, covering services and supply, and requires fast-track procedures, tacit approval where national law allows, and administrative support focused on SMEs and mid-caps. Member states must publish centralised online information on procedures, funding and applicable environmental, health and safety laws, and ensure impartial single points of contact with sufficient staff and digital tools. It adds rules on spatial planning, urgent dispute resolution, cross-border coordination, and annual reporting by member states to the Commission on permits, tacit approvals and SME support.
Standpunkt. The committees adopt Parliament's position at first reading with amendments to the Commission proposal, setting a 50-working-day permit limit, single points of contact, tacit approval rules, SME support and annual reporting.
Kernpunkte
- Defines a defence readiness project as activities, investments or measures primarily intended to enhance the defence readiness of one or several member states, including developing or modernising the defence industry.
- Defines the defence industry to include undertakings developing, producing, manufacturing or supplying defence-related products and those providing services that enhance member states' defence readiness.
- Requires each member state to establish or designate a single point of contact within 3 months of entry into force, acting as a single interface for each project.
- Requires the single point of contact to coordinate the permit process, give information on completeness and documentation, and allow electronic submission via a secure interoperable portal.
- Requires member states to give single points of contact and competent authorities enough qualified staff and financial, technical and digital resources, and lets the Commission assist with capacity building on request.
- Requires member states to publish centralised online information on permit procedures, funding possibilities, standardised application templates and applicable environmental, health and safety laws.
- Requires administrative support for all project promoters, with particular attention to SMEs and mid-caps, including compliance assistance, cross-border coordination and a dedicated SME desk.
- Sets the permit-granting process at no more than 50 working days from acknowledgement of completeness, with a one-time extension of up to 25 working days and a further extension of up to 50 working days in exceptional cases.
- Requires the single point of contact to acknowledge completeness within 12 working days, and provides that permits are deemed granted if no outcome is notified within the time limit, unless national law excludes tacit approval.
- Requires national, regional and local authorities to include provisions for defence readiness activities and infrastructure in spatial plans, taking account of cyber and hybrid threat security considerations.
- Requires dispute resolution procedures, litigation, appeals and administrative proceedings on defence readiness projects to be treated as urgent where national law provides for urgency procedures, without undermining the right to an effective remedy.
- Requires each member state to submit an annual statistical report to the Commission on applications, permits granted, tacit approvals and SME support, and empowers the Commission to adopt implementing acts on the reporting template.
Wen es betrifft
- Defence industry undertakings, including SMEs and mid-caps, which gain fast-track permits and dedicated support.
- Member states, which must set up single points of contact, publish information and report annually.
- National, regional and local planning authorities, which must include defence readiness provisions in spatial plans.
- Project promoters, who can submit documents electronically and benefit from tacit approval rules.
- The Commission, which assists with capacity building and adopts implementing acts on reporting.
Zahlen und Fristen
- EUR 800bn: possible defence investment over the next four years under the ReArm Europe Plan/Readiness 2030.
- 3 months after entry into force: deadline for member states to establish or designate a single point of contact.
- 6 months: maximum period for a member state's time-bound plan to achieve full e-processing capability.
- 50 working days: maximum duration of the permit-granting process from acknowledgement of completeness.
- 25 working days: maximum one-time extension of the permit-granting time limit.
- 50 working days: further extension in exceptional cases, decided within 25 working days of the start of the process.
- 12 working days: deadline for the single point of contact to acknowledge completeness of an application.
- 10 days, and not later than 3 working days: deadline for written confirmation of tacitly granted permits.
Rechtsgrundlage. Article 294(2) and Article 114 of the Treaty on the Functioning of the European Union.
Von KI aus dem Volltext geschrieben · jede Zahl stammt aus dem Text · ¶ öffnet den Absatz · 16. Sept. 2026 · KI-Texte gibt es bisher nur auf Englisch. · Problem melden
Volltext
Den Wortlaut des Dokuments zeigt diese Website bisher nur auf Englisch. Deutsche Fassung auf der Website des Parlaments →
Der Vorschlag der Kommission COM(2025)0821 in der auf EUR-Lex veröffentlichten Fassung; eingearbeitet sind die 63 Änderungsanträge, die das Parlament am 16. September 2026 angenommen hat; 12 davon konnten nicht zugeordnet werden.
142 Absätze, 51 geändert, 51 Änderungsanträge übernommen, 12 nicht zugeordnet
Ausgangstext: COM(2025)0821 auf EUR-Lex →
gestrichen: Durchgestrichene Wörter werden aus dem Vorschlag gestrichen, eingefügt: markierte Wörter eingefügt; ein Strich am Rand kennzeichnet einen geänderten Absatz.
Zu einer Änderung springen (51)
- Änd. 1 · Recital 1
- Änd. 2 · Recital 1 a (new)
- Änd. 3 · Recital 2
- Änd. 4 · Recital 3
- Änd. 5 · Recital 4
- Änd. 6 · Recital 5
- Änd. 7 · Recital 5 a (new)
- Änd. 8 · Recital 6
- Änd. 9 · Recital 7 a (new)
- Änd. 10 · Recital 8
- Änd. 11 · Recital 8 a (new)
- Änd. 12 · Recital 9
- Änd. 13 · Recital 9 a (new)
- Änd. 14 · Recital 10 a (new)
- Änd. 15 · Recital 10 b (new)
- Änd. 16 · Recital 10 c (new)
- Änd. 17 · Recital 11
- Änd. 18 · Recital 11 a (new)
- Änd. 19 · Recital 11 b (new)
- Änd. 20 · Recital 12
- Änd. 21 · Recital 12 a (new)
- Änd. 22 · Recital 14
- Änd. 23 · Recital 14 a (new)
- Änd. 24 · Recital 14 b (new)
- Änd. 25 · Recital 14 c (new)
- Änd. 26 · Recital 15
- Änd. 27 · Recital 17
- Änd. 28 · Article 1 – paragraph 1 – point 1
- Änd. 29 · Article 1 – paragraph 1 – point 2
- Änd. 30 · Article 1 – paragraph 1 – point 3
- Änd. 31 · Article 1 – paragraph 1 – point 6
- Änd. 32 · Article 2 – title
- Änd. 33 · Article 2 – paragraph 1
- Änd. 34 · Article 2 – paragraph 2
- Änd. 35 · Article 2 – paragraph 4
- Änd. 37 · Article 2 – paragraph 5
- Änd. 38 · Article 2 – paragraph 6
- Änd. 39 · Article 2 – paragraph 7
- Änd. 40 · Article 2 – paragraph 8
- Änd. 44 · Article 3 – paragraph 1 – introductory part
- Änd. 45 · Article 3 – paragraph 1 – point d
- Änd. 48 · Article 4 – paragraph 1 – introductory part
- Änd. 49 · Article 4 – paragraph 1 – point a
- Änd. 52 · Article 5 – paragraph 1
- Änd. 54 · Article 5 – paragraph 2
- Änd. 55 · Article 5 – paragraph 3
- Änd. 56 · Article 5 – paragraph 4
- Änd. 57 · Article 5 – paragraph 6
- Änd. 59 · Article 5 – paragraph 8
- Änd. 60 · Article 6 – paragraph 1
- Änd. 62 · Article 7 – paragraph 1
Begründung 48 Absätze
EXPLANATORY MEMORANDUM
CONTEXT OF THE PROPOSAL
Reasons for and objectives of the proposal
The Russian invasion of Ukraine has underscored the need for a strengthened EU-wide market for defence products, capable of supporting the defence readiness of Member States in the face of emerging security threats. The ongoing conflict has exposed vulnerabilities in the European defence landscape, highlighting the importance of a cohesive and resilient defence industrial base. A well-functioning EU defence market is essential to ensure that Member States have access to the necessary defence capabilities, technologies and products to respond effectively to current and future security challenges.
The impact of the changing geopolitical landscape on the EU defence market has been significant, with disruptions to supply chains, increased demand for defence products and a growing need for interoperable and innovative solutions. However, existing legislation impacting the EU defence market is not adapted to the current challenges, hindering the ability of Member States to respond rapidly and effectively to emerging threats. The existing framework, developed in peacetime, is often slow to respond to the urgent needs of Member States, and fails to provide the necessary incentives for investment in defence research and development, notably to facilitate defence investments of at least EUR 800bn over the next four years, as indicated in the Joint White paper on defence readiness.
In response to these challenges, the EU must take steps to strengthen the EU-wide market for defence products, promoting a more integrated and competitive defence industrial base. By creating a more robust, resilient EU defence market and developing the necessary infrastructure the EU can support the defence readiness of Member States, promote European strategic autonomy and contribute to a more stable and secure European security environment.
This proposal is a part of the Defence Readiness Omnibus. In addition to the simplification of existing regulation contained in the other acts, this proposal sets forward the establishment of a dedicated fast-track procedure for permit granting related to defence readiness.
Consistency with existing policy provisions in the policy area
The proposal aims to adapt the provisions governing the EU-wide defence market to the current security scenario, by introducing targeted adjustments that simplify administrative procedures, cut red tape and provide more flexible solutions. By streamlining procedures and reducing bureaucratic obstacles, the proposal seeks to create a more agile and responsive EU defence market, better equipped to support the defence readiness of Member States and promote the development of a competitive and innovative European defence industry.
Consistency with other Union policies
The proposal contributes to the objectives of enhancing the EU's defence capabilities and strengthening its strategic autonomy, while also supporting the development of innovative and sustainable defence technologies. The fast-track permitting procedure established by this proposal will facilitate the rapid deployment of defence readiness projects and expected defence investments of at least EUR 800bn over the next four years, ensuring that the EU's defence industry can respond quickly to emerging security challenges and contribute to the protection of European citizens. By streamlining the permitting process, this proposal will also help to reduce administrative burdens and costs for defence companies, allowing them to focus on the delivering on the needs of the EU Member States development of cutting-edge technologies and the creation of high-skilled jobs.
The proposed measures will also contribute to the EU's resilience and strategic autonomy by ensuring the security of supply of key defence-related technologies, which is crucial for supporting the development of the EU's defence capabilities and for public order and security. By promoting the development of a strong and innovative defence industry, this proposal will help to reduce the EU's dependence on third-country suppliers and enhance its ability to respond to emerging security challenges.
The proposal is consistent with the EU policies in the fields of safety, health, environment as it does not lower standards but aims at accelerating the procedures. The proposal is without prejudice to the level of scrutiny foreseen by the applicable permit processes.
LEGAL BASIS, SUBSIDIARITY AND PROPORTIONALITY
Legal basis
The legal basis for this proposal is Article 114 TFEU. The measures proposed in this regulation have as their objective to preserve the well-functioning of the internal market, particularly the EU-wide Defence Market. In view of the current geopolitical context, the EU Member States need to rapidly increase their defence readiness. To do that, investments in defence readiness will be necessary for the functioning of the EU-wide Defence Market (such as manufacturing plants, testing facilities, as well as the necessary infrastructure.). Such development projects aimed at increasing the defence readiness of Member States or the EU require several permits to be granted. A situation in which some parts of the internal market foresee a much shorter permit-granting process would result in a serious risk to the smooth operation of the internal market. This proposal ensures that the treatment of the permit-granting process for defence readiness projects is fast and harmonized throughout the Member States.
Subsidiarity (for non-exclusive competence)
The objectives of the proposal cannot be achieved by Member States acting alone, as the problems are of a cross-border nature. The defence industry is highly integrated and interconnected, with companies operating across multiple Member States and relying on complex supply chains that transcend national borders. The proposed actions focus on areas where there is a demonstrable value added in acting at Union level due to the scale, speed and scope of the efforts needed. By establishing a fast-track permitting procedure at EU level, the proposal aims to create a level playing field for defence companies operating in the EU, ensuring that they can respond quickly and effectively ramp up defence industrial production. The EU's collective defence efforts require a coordinated approach, and the proposed mechanism will facilitate the rapid deployment of defence readiness projects.
A lack of coordination between Member States when it comes to the treatment of the permit-granting process for defence readiness projects could result in a regulatory race to the bottom or certain parts of the internal market gaining a competitive advantage. This would be undesirable as it would negatively affect the security of supply of defence products, potentially compromising the EU's ability to respond to emerging security threats. The proposed mechanism does not influence the factual basis of the granting of the permits concerned but rather establishes a single point of contact in Member States and a more agile way of dealing with permit applications. This will enable defence companies to obtain the relevant permits more efficiently, while ensuring that the necessary environmental, health and safety standards are upheld.
Proportionality
The proposal complies with the proportionality principle in that it does not go beyond the minimum required to achieve the stated objectives at the European level and which is necessary for that purpose.
In view of the unprecedented geopolitical situation, the significant threat for security of the Union and the unprecedented scale of defence in investments in the next four years, the proposed policy approach is proportionate to the scale and gravity of the problems that have been identified. The proposal is designed to strengthen the defence readiness of Member States via measures to ensure a smooth functioning the EU-wide defence market in face of the massive and urgent ramp-up of the defence production capacities.
Choice of the instrument
The Commission proposes a Regulation of the European Parliament and of the Council. This is the most suitable legal instrument as only a Regulation, with its uniform application, binding nature and direct applicability, can provide the necessary degree of uniformity needed to facilitate the deployment of defence readiness projects.
RESULTS OF EX-POST EVALUATIONS, STAKEHOLDER CONSULTATIONS AND IMPACT ASSESSMENTS
Ex-post evaluations/fitness checks of existing legislation
N/A
Stakeholder consultations
The stakeholder consultation process was comprehensive, comprising a public survey that was open until 22 April 2025, as well as a series of targeted meetings with Member States, relevant business representatives from the Union and other key stakeholders. Through this consultation process, combined with the Commission's experience in implementing the relevant legislation, key blockages and challenges within the EU regulatory environment were identified. Based on valuable input received and the Commission's expertise, the proposals outlined in this Regulation aim to address these key issues and improve the overall effectiveness of the EU regulatory framework.
Collection and use of expertise
N/A
Impact assessment
The European Council called in its Conclusions of 6 March 2025 called on the Commission to accelerate the “work on all strands to decisively ramp up Europe’s defence readiness within the next five years”. Furthermore, in the same conclusions the European Council expressly called on the Commission to rapidly follow up with simplification on security and defence.
Due to the urgent nature of the proposal, which is designed to support the rapid adaptation of the European defence industry to the new geopolitical environment and aid a country at war as of the beginning of 2023, it was not possible to deliver an impact assessment prior to the adoption of the Defence Readiness Omnibus. Within 3 months after the adoption of this proposal the Commission will present a Staff Working document to justify in detail this legislative action and explain its appropriateness to achieve the identified policy objectives in accordance with the relevant Better Regulation rules.
The proposal concerns limited and targeted changes of legislation. They are based on experience from implementing legislation. The changes do not have significant impact on the policy but only ensure a more efficient and effective implementation. Their targeted nature and the lack of relevant policy options make an impact assessment not necessary. However, the attached Communication looks at elements on the impact of such measures, including the analysis of results of an EU public survey undertaken in this context.
Regulatory fitness and simplification
The proposal to establish a single point of contact for permit-related proceedings for the defence sector, along with a fast-track permitting procedure, is expected to have a positive impact on minimizing compliance costs for SMEs, large companies and other stakeholders in the defence sector. By establishing a single point of contact in Member States, companies will no longer need to navigate multiple authorities and administrative bodies to obtain permits, reducing the time and resources spent on administrative tasks. This simplification of administrative procedures will significantly reduce uncertainty, providing defence companies with greater certainty and predictability, allowing them to plan their defence readiness activities with more confidence.
The fast-track procedure, which presumes a permit was granted if no reply is received by the set deadline, will also accelerate the permit issuance process, enabling defence companies to start their projects sooner, reducing delays and minimizing the associated costs. This streamlined process will enhance the competitiveness of the EU defence sector, particularly for SMEs, which will be able to respond more quickly to changing market conditions and customer needs. A more efficient and predictable permit issuance process will make the EU defence sector more attractive to investors, both domestic and foreign, which could lead to increased investment and growth in the sector.
This will facilitate trade in the defence sector, particularly for SMEs, which will be able to export their products and services more easily, contributing to the growth of international trade. The establishment of a single point of contact and a fast-track procedure will also facilitate cooperation between EU defence companies and their international partners, promoting the development of joint projects and collaborations, while ensuring compliance with international agreements and proportionate requirements to minimize the administrative burden on SMEs and other stakeholders.
Fundamental rights
N/A
BUDGETARY IMPLICATIONS
Upon request by a Member State, assistance for capacity-building in support of the establishment or the operation of a single contact point will be eligible for funding under the European Defence Industry Programme (EDIP) when adopted and within the agreed envelope of the programme. The capacity-building support under this proposal falls within the scope of support actions under EDIP. Due to the limited budgetary implications, no legislative financial statement will be prepared.
OTHER ELEMENTS
Implementation plans and monitoring, evaluation and reporting arrangements
N/A
Detailed explanation of the specific provisions of the proposal
This Regulation sets up streamlined permitting processes for defence readiness projects. All defence readiness projects will benefit from Member States designating a national competent authority acting as a single point of contact, in charge of coordination and facilitation of permitting, guiding economic operators, ensuring that information is publicly accessible and that all documents can be digitally submitted. The Regulation sets detailed timelines for permitting procedures. The proposal is consistent with Union legislation on permitting.
Proposal for a regulation of the European Parliament and of the Council
On the acceleration of permit-granting for defence readiness projects
THE EUROPEAN PARLIAMENT AND THE COUNCIL OF THE EUROPEAN UNION,
Having regard to the Treaty on the Functioning of the European Union, and in particular Article 114 thereof,
Having regard to the proposal from the European Commission,
After transmission of the draft legislative act to the national parliaments,
Having regard to the opinion of the European Economic and Social Committee,
Acting in accordance with the ordinary legislative procedure,
Whereas:
(1)eingefügt: (1) The Union is facing an acute and growing threat, as underscored in the Joint White Paper on European Defence Readiness gestrichen: 2030,eingefügt: 20302, linked to the return of full-scale conflict in gestrichen: Europe.eingefügt: Europe gestrichen: Ineingefügt: in gestrichen: responseeingefügt: the gestrichen: toeingefügt: context gestrichen: thiseingefügt: of gestrichen: escalatingeingefügt: Russia’s gestrichen: challenge,eingefügt: war gestrichen: iteingefügt: of gestrichen: iseingefügt: aggression gestrichen: imperativeeingefügt: against gestrichen: thateingefügt: Ukraine eingefügt: and the gestrichen: Unioneingefügt: associated gestrichen: takeseingefügt: hybrid gestrichen: decisiveeingefügt: activities gestrichen: actioneingefügt: targeting gestrichen: toeingefügt: the gestrichen: bolstereingefügt: Union eingefügt: and its gestrichen: defenceeingefügt: Member gestrichen: readiness.eingefügt: States, gestrichen: Thereeingefügt: including gestrichen: iseingefügt: sabotage, gestrichen: urgencyeingefügt: cyberattacks, gestrichen: toeingefügt: disinformation, gestrichen: rampeingefügt: economic gestrichen: upeingefügt: coercion gestrichen: Europeaneingefügt: and gestrichen: defenceeingefügt: hostile gestrichen: readinesseingefügt: intelligence gestrichen: toeingefügt: operations, gestrichen: ensureeingefügt: as gestrichen: thateingefügt: well gestrichen: Europeeingefügt: as gestrichen: haseingefügt: repeated gestrichen: aeingefügt: violations gestrichen: strongeingefügt: of eingefügt: EU and gestrichen: sufficienteingefügt: NATO gestrichen: Europeaneingefügt: airspace, gestrichen: defenceeingefügt: and gestrichen: postureeingefügt: also gestrichen: byeingefügt: an gestrichen: 2030eingefügt: evolving gestrichen: ateingefügt: transatlantic eingefügt: security posture. Accordingly, the gestrichen: latest.eingefügt: Union gestrichen: Basedeingefügt: must gestrichen: oneingefügt: reinforce gestrichen: projectionseingefügt: its gestrichen: ofeingefügt: strategic gestrichen: gradualeingefügt: autonomy gestrichen: take-upeingefügt: and gestrichen: ofeingefügt: resilience. gestrichen: theeingefügt: In gestrichen: instrumentseingefügt: response gestrichen: proposedeingefügt: to gestrichen: undereingefügt: this eingefügt: escalating challenge, it is imperative that the gestrichen: ReArmeingefügt: Union gestrichen: Europeeingefügt: takes gestrichen: Plan/Readinesseingefügt: decisive gestrichen: 2030,eingefügt: action gestrichen: defenceeingefügt: to gestrichen: investmenteingefügt: bolster gestrichen: couldeingefügt: its gestrichen: reacheingefügt: defence gestrichen: ateingefügt: readiness gestrichen: leasteingefügt: and gestrichen: EUReingefügt: overall gestrichen: 800bneingefügt: societal gestrichen: overeingefügt: resilience, gestrichen: theeingefügt: while gestrichen: nexteingefügt: upholding gestrichen: foureingefügt: the gestrichen: years.eingefügt: Union’s gestrichen: Aeingefügt: values gestrichen: crucialeingefügt: and gestrichen: aspecteingefügt: democratic gestrichen: ofeingefügt: principles, gestrichen: thiseingefügt: taking gestrichen: efforteingefügt: into gestrichen: iseingefügt: account the gestrichen: needeingefügt: recommendations gestrichen: toeingefügt: identified gestrichen: rampeingefügt: in gestrichen: upeingefügt: high-level gestrichen: theeingefügt: reports gestrichen: Union'seingefügt: by gestrichen: defenceeingefügt: Mario gestrichen: productioneingefügt: Draghi, gestrichen: capacity,eingefügt: Sauli gestrichen: enablingeingefügt: Niinistö gestrichen: iteingefügt: and gestrichen: toeingefügt: Enrico gestrichen: respondeingefügt: Letta. gestrichen: effectivelyeingefügt: There eingefügt: is urgency to gestrichen: emergingeingefügt: ramp gestrichen: securityeingefügt: up gestrichen: threats.eingefügt: European gestrichen: Ineingefügt: defence gestrichen: ordereingefügt: readiness to gestrichen: achieveeingefügt: ensure that gestrichen: goal,eingefügt: Europe gestrichen: regulatoryeingefügt: has gestrichen: simplificationeingefügt: a eingefügt: strong and gestrichen: harmonisationeingefügt: sufficient gestrichen: areeingefügt: European gestrichen: essential.eingefügt: defence gestrichen: Byeingefügt: posture gestrichen: streamliningeingefügt: by gestrichen: andeingefügt: 2030 gestrichen: aligningeingefügt: at gestrichen: regulatoryeingefügt: the gestrichen: frameworks,eingefügt: latest. gestrichen: theeingefügt: It gestrichen: Unioneingefügt: is gestrichen: caneingefügt: particularly gestrichen: createeingefügt: important gestrichen: aeingefügt: to gestrichen: moreeingefügt: close gestrichen: conduciveeingefügt: the gestrichen: environmenteingefügt: most gestrichen: foreingefügt: critical gestrichen: defenceeingefügt: capability gestrichen: industrieseingefügt: shortfalls, gestrichen: toeingefügt: in gestrichen: operate,eingefügt: particular gestrichen: innovate,eingefügt: those gestrichen: andeingefügt: outlined gestrichen: produceeingefügt: in the gestrichen: necessaryeingefügt: Defence gestrichen: capabilitieseingefügt: Readiness eingefügt: Roadmap 2030, ensuring that efforts to gestrichen: ensureeingefügt: close gestrichen: Europeaneingefügt: such gestrichen: securityeingefügt: shortfalls eingefügt: are carried out in coherence and gestrichen: defenceeingefügt: mutual gestrichen: readiness.eingefügt: reinforcement with activities carried out within NATO, while avoiding unnecessary duplications.
(1a)eingefügt: Based on projections of gradual take-up of the instruments proposed under the ReArm Europe Plan/Readiness 2030, defence investment could reach at least EUR 800bn over the next four years. Such a level of investment also provides an opportunity to develop the European Defence Technological and Industrial Base (EDTIB) within the single market, by enabling competitive, innovative and diverse defence technology actors to participate effectively in the EDTIB, while ensuring fair participation in the defence market, including SMEs, and in full compliance with Union and national social, labour, safety and environmental standards. A crucial aspect of this effort is the need to ramp up the Union's defence production capacity, enabling it to respond effectively to emerging security threats. In order to achieve that goal, regulatory simplification and harmonisation are essential in a way that improves efficiency, transparency, and accountability. By streamlining and aligning regulatory frameworks, the Union can create a more conducive environment for defence industries to operate, innovate, and produce the necessary capabilities to ensure European security and defence readiness. At the same time, efforts to promote a coherent approach to standardisation should be encouraged in order to strengthen interoperability and support a more efficient and coordinated development of defence capabilities across the Union.
(2)eingefügt: (2) In this context, defence readiness should be understood as the ability of Member States to anticipate, prevent, and respond to defence related crises, as referred to in Directive 2009/81/EC of the European Parliament and of the gestrichen: Councileingefügt: Council3 through a proactive and coordinated approach. This includes ensuring the availability of defence industrial capacity required to acquire and maintain the necessary resources, capabilities, and infrastructure with the aim of responding effectively to such crises.eingefügt: Furthermore, defence readiness should also include broader preparedness, strengthening the resilience of society as a whole, to hybrid threats, disinformation campaigns, cyber attacks and other non-military forms of influence. This Regulation should apply solely to projects that contribute to the Union’s and Member States’ defence readiness and abide by the rules governing the internal market to ensure fair competition.
(3)eingefügt: (3) Setting up or extending facilities, infrastructure and undertaking activities related to defence readiness often requires applying for several relevant permits and approvals. Existing permitting processes for assessments across various areas are often lengthy and cumbersome. eingefügt: Small mid-caps and SMEs in particular are disproportionately affected, which has negative consequences for the entire supply chain. Those procedures currently lack Union-wide provisions for fast-track processes specific to defence readiness activities, which impedes the ramp-up of defence production and related infrastructure in a timely manner and defence readiness activities and investments that are crucial for meeting emerging security demands.
(4)eingefügt: (4) The national permit-granting process ensures that defence readiness projects are gestrichen: safe,eingefügt: carried gestrichen: secureeingefügt: out eingefügt: safely, securely and gestrichen: complyeingefügt: in eingefügt: full compliance with eingefügt: relevant environmental, social eingefügt: labour and other safety gestrichen: requirements.eingefügt: requirements eingefügt: throughout all stages of the process. Union environmental law sets common conditions for the content of the national permit-granting process, thereby ensuring a high level of environmental gestrichen: protectioneingefügt: protection. eingefügt: In light of the acute threat posed by Russia’s war of aggression against Ukraine and gestrichen: allowingeingefügt: the gestrichen: foreingefügt: accompanying eingefügt: hybrid activities directed against the gestrichen: sustainableeingefügt: Union gestrichen: exploitationeingefügt: and eingefügt: its Member States, it is essential that the application of eingefügt: Union and national rules enables the eingefügt: rapid and efficient implementation of defence readiness projects, while remaining consistent with the Union’s gestrichen: potentialeingefügt: environmental gestrichen: alongeingefügt: acquis. eingefügt: This approach would enable the eingefügt: sustainable and responsible development of Europe’s defence industrial and raw materials gestrichen: valueeingefügt: capacities, gestrichen: chain.eingefügt: while avoiding unnecessary administrative delays that could hinder security preparedness.
(5)gestrichen: At the same time,eingefügt: (5) gestrichen: theeingefügt: The unpredictability, complexity and, often, excessive length of national permit-granting gestrichen: processeseingefügt: procedures undermine gestrichen: the investment security eingefügt: certainty and planning needed for the effective strengthening of Member States defence gestrichen: readiness.eingefügt: readiness eingefügt: and risk discouraging innovative SMEs and small mid-caps from entering into or scaling within the defence sector. The structure and length of a permit-granting process for relevant projects can also differ greatly between Member States. Therefore, to ensure and speed up their effective implementation, Member States should apply streamlined and predictable permit-granting processes to defence readiness projects.
(5a)eingefügt: Defence readiness projects, including related industrial and governmental activities can, where applicable, fall within the scope of existing Union provisions allowing derogations, including from Union environmental law, on grounds of “overriding public interest”, “public safety” or “crisis” response. Member States can therefore, where so provided under national law, assess on a case-by-case basis whether permit-granting procedures for defence readiness projects can rely on those existing derogations. Any such assessment should be carried out in accordance with the conditions set out in the relevant Union and national law. Where compensatory or mitigating measures are required in the framework of the permit-granting process, they should ensure that the interests of relevant sectors are safeguarded in a proportionate manner, while preserving all obligations and safeguards laid down in the applicable legal frameworks and with a view to the timely achievement of the Defence Readiness 2030 objective.
(6)eingefügt: (6) While certain Member States have taken or are likely to take measures to accelerate the permission-granting processes for the defence industry, this may be done in diverging ways which would result in barriers to the functioning of the internal market in the defence sector. Divergent national legislation, regarding the planning permit-granting process of defence projects have proven to become bottlenecks for European relevant defence products supply chains. To ensure the functioning of the internal market, it is necessary to establish harmonised rules eingefügt: and timelines for the acceleration of the permit-granting processes.
(7)While Union institutions can provide guidance and frameworks, the responsibility for authorisation and facilitating fast-track permitting processes resides primarily with Member States. Member States are best positioned to implement changes that cater to their specific administrative and regulatory landscapes.
eingefügt: (7 a) The application of this Regulation should fully respect the sole responsibility of the Member States for safeguarding their national security. Essential functions, including the defence of the territory, the maintenance of law and order and the protection of public security, remain within national competence and are not affected by this Regulation. Member States can maintain or introduce extraordinary national permitting procedures, provided that such measures do not undermine the functioning of the internal market for defence readiness projects within the scope of this Regulation.
(8)eingefügt: (8) There is a pressing need to reduce the complexity and duration of permitting processes for defence readiness gestrichen: projects.eingefügt: projects, eingefügt: while ensuring that such processes are accessible to mid-caps, small mid-caps and SMEs contributing to the development of new and emerging defence technologies. By establishing national permitting frameworks that prioritise these projects and ensure their rapid processing, the Union aims to enhance its defence production capacity and readiness by 2030 at the latest.
(8a)eingefügt: In situations of supply chain crisis, uncertainty can hinder timely decisions and investment planning. Member States are therefore encouraged to publish and periodically update clear, accessible online information on relevant risks and bottlenecks, in line with national security and confidentiality requirements, in order to help companies anticipate and adjust their production, support the efficient allocation of scarce resources to strategically important projects and strengthen the Union’s defence industrial resilience and strategic autonomy.
(9)eingefügt: (9) In order to address these challenges, the defence industry should benefit of rules proven to be effective in streamlining industrial permitting gestrichen: processes.eingefügt: processes eingefügt: and boosting innovative defence industrial actors. Aiming to reduce permitting deadlines for defence industry activities, including construction of new plants and related infrastructure, expansion of existing facilities, establishment of testing sites, training eingefügt: certifying, and gestrichen: certifyingeingefügt: research eingefügt: and development, including prototype construction and technology transfer, while also building on and broadening existing applicable provisions.eingefügt: A more agile regulatory framework will free up resources for technological innovation, encourage production modularity and promote the establishment of cross-border consortia that can bridge capacity gaps more quickly.
(9a)eingefügt: To ensure that a streamlined permitting process and prioritisation processes cover the whole defence value chain, the concept of the defence industry should include not only undertakings manufacturing defence-related products within the meaning of Directive 2009/43/EC, but also undertakings providing services that directly enhance the defence readiness of one or more Member States. Furthermore, to address the principal bottlenecks in defence investments, the permit-granting process under this Regulation should cover all relevant permissions, including permits, approvals or licences required to build, expand, convert, operate or repurpose installations, equipment or activities for the manufacturing of defence products or components, or for other activities forming part of a defence readiness project. Bringing all such permissions into a single, coordinated and time-bound procedure, from the acknowledgement of the completeness of an application to the notification of the final decision by the single point of contact, reduces fragmentation, shortens procedural timelines and enhances legal certainty.
(10)Complying with Union law, including for instance in relation to water, waste management, air, ecosystems, habitats, archaeological, biodiversity and birds’ protection, are integral part of the permit granting procedure, also for the defence sector. Such rules are an essential safeguard to ensure negative impacts are prevented or minimised. However, to ensure that permit granting procedures for defence readiness projects are predictable and timely, any potential to streamline the required assessments and authorisations while not lowering the level of, for instance, environmental protection, should be realised. In that regard, it should be ensured that the necessary assessments are bundled to prevent unnecessary overlap.
(10a)eingefügt: Member States should ensure that permitting and assessment procedures required under national law are organised in a coordinated manner that complements those required under Union law, avoiding overlap, duplication and unnecessary administrative delays, while maintaining a high level of environmental protection. Where appropriate, such procedures should be coordinated or combined to provide an efficient, predictable and transparent process for project promoters.
(10b)eingefügt: To safeguard trust in the simplification of administrative processes, accelerated procedures and the internal market, Member States should ensure the impartiality of single points of contact and all competent national authorities involved in the permit-granting process, including through maintaining fair-competition and conflict-of-interest principles, transparency of decision-making, publication of non-confidential statistics on permit decisions. Those measures should ensure non-discriminatory access for SMEs and companies of all sizes across the Union. Member States and the Commission should ensure that appropriate measures are in place to prevent, detect, and correct any risk of fraud or corruption.
(10c)eingefügt: This Regulation clarifies that, when a project is subject to an environmental impact assessment pursuant to Directive 2011/92/EU, the steps (i) and (ii) of the environmental impact assessment timeline should not be included in the duration of the permit-granting process established by this Regulation. This Regulation also requires single points of contact to provide information to project promoters about the requirement to carry out an environmental impact assessment, as well as the scope and level of detail of such assessment.
(11)eingefügt: (11) To facilitate the efficient and timely processing of administrative permitting applications related to defence readiness activities and the scaling up of defence production, eingefügt: and supporting mid-caps, small mid-caps and SMEs, Member States need to ensure that the competent national authorities implement fast-track procedures. Those authorities should provide the most rapid legal treatment possible for such applications, thereby enabling timely responses to defence readiness needs.eingefügt: The competent authorities have flexibility to prolong the standard fast-track timeline for the reasons of potential risks to health, safety, the environment, and national security. To ensure that these exceptional circumstances are treated in rigorous and transparent manner, it is essential that competent authorities do not merely assert the existence of exceptional circumstances but substantiate such claims with verifiable evidence.
(11a)eingefügt: In addition, in order to further accelerate and streamline the permit issuing process, the principle of tacit approval should apply to the application for a permit except where that principle is in contradiction with the existing national legal system of a Member State. Therefore, an application for a permit should be considered granted if the project promoter has not been informed by the single point of contact within the applicable deadline of the outcome of the permit-granting process.
(11b)eingefügt: Where a permit for a defence readiness project is implicitly granted, such approval should not exempt the project promoter or the competent authority from full compliance with applicable Union and national law, including provisions on environmental protection and on the health and safety of workers.
(12)eingefügt: (12) Establishing gestrichen: aeingefügt: one eingefügt: or more single gestrichen: pointeingefügt: points of contact for industry applications regarding permits related to defence gestrichen: activitieseingefügt: activities. is intended to streamline communication, eingefügt: clarify responsibilities, reduce administrative burdens and further expedite the permitting process with clear and legally binding deadlines, thereby providing efficient pathway for defence-related industrial applications. Moreover, it will provide certainty to investors by ensuring the rapid treatment of permit applications and limiting the risks to investments related to lengthy procedures.eingefügt: Member States should provide their single points of contact, as well as any authority involved in the permit-granting process, with sufficient personnel and resources.
(12a)eingefügt: In Member States with a federal or otherwise decentralised administrative structure, or where regional or local authorities are required to be involved in the approval process or to adopt the relevant decisions, the functions of the single point of contact may be exercised through a coordinating structure involving regional or local authorities, provided that it is ensured that project promoters have one clearly identified interface for each project, and that that interface is coordinated and streamlined. Member States should make best efforts to ensure that project promoters, in particular SMEs and small mid-caps, can easily identify and access the competent single point of contact for their specific project. Flexibility should be ensured to allow several competent authorities to operate as single points of contact where necessary, provided that clear coordination mechanisms are in place and that project promoters have one clearly identified coordinating authority acting as the sole interface for each project. Such arrangements should avoid duplication or fragmentation of procedures and preserve the efficiency and purpose of the single-point-of-contact system.
(13)To accelerate reaching full operational capacity of the single contact points Member States should, to the extent possible, take advantage of possible complementarity with existing single contact points, for example those established under Regulation (EU) 2024/1735 of the European Parliament and of the Council or Regulation (EU) 2024/1252 of the European Parliament and of the Council.
(14)eingefügt: (14) Furthermore, Member States should provide the necessary administrative support to defence readiness projects located on their territory, to facilitate their timely and effective implementation, paying particular attention to the needs of small and medium-sized enterprises eingefügt: which often face higher relative compliance costs and gestrichen: mid-capeingefügt: limited gestrichen: enterpriseseingefügt: administrative gestrichen: involvedeingefügt: capacity. gestrichen: ineingefügt: To gestrichen: thoseeingefügt: that gestrichen: projects,eingefügt: end, gestrichen: byeingefügt: the gestrichen: providingeingefügt: single gestrichen: assistanceeingefügt: point gestrichen: regardingeingefügt: of gestrichen: complianceeingefügt: contact gestrichen: witheingefügt: should gestrichen: applicableeingefügt: include gestrichen: administrativeeingefügt: dedicated eingefügt: support functions for SMEs and gestrichen: reportingeingefügt: midcaps, gestrichen: obligations,eingefügt: such gestrichen: informingeingefügt: as gestrichen: theeingefügt: helpdesks, gestrichen: publiceingefügt: harmonised gestrichen: toeingefügt: templates gestrichen: increaseeingefügt: and gestrichen: acceptanceeingefügt: digital gestrichen: ofeingefügt: tools, gestrichen: theeingefügt: offering gestrichen: projectseingefügt: clear eingefügt: guidance on documentation and gestrichen: guidingeingefügt: compliance gestrichen: projecteingefügt: requirements gestrichen: promoterseingefügt: and gestrichen: througheingefügt: assistance eingefügt: throughout the permit-granting gestrichen: process.eingefügt: process, so that smaller actors can participate effectively and without disproportionate administrative burden.
(14a)eingefügt: To ensure effective, transparent and comparable implementation, the performance of single points of contact should be assessed through common Union-wide indicators and data collected to be submitted by each Member State to the Commission annually.
(14b)eingefügt: Transparency and equal access to information are crucial for the effective implementation of permit-granting processes. Member States should ensure that all project promoters, regardless of their Member State of establishment, have support and equal access to centralised, easily accessible online information. This includes details on single points of contact, permit-granting procedures, dispute resolution mechanisms, financing and investment services, and available Union or national funding instruments.
(14c)eingefügt: To avoid the proliferation of uncoordinated administrative platforms, Member States should design digital tools supporting this Regulation that are interoperable in order to allow for reusing information already submitted under other Union or national procedures and offer a single, user-friendly digital interface, particularly benefiting SMEs and mid-caps.
(15)eingefügt: (15) The Commission gestrichen: mayeingefügt: should, eingefügt: upon request by a Member State offer capacity-building support to the single point of contact, including technical assistance, training, monitoring and evaluation, with the aim of developing and strengthening the abilities, processes and resources that the single points of contacts need to develop for the purposes of this Regulation. Such support may be requested by Member States and will fall within the scope of supporting actions under eingefügt: Regulation (EU) 20XX/XXXX on the European Defence Industry Programme [reference to be added once EDIP is adopted].
(16)In order to ensure clarity about the permitting status of defence readiness projects and to limit the effectiveness of potential abusive litigation, while not undermining effective judicial review, Member States should ensure that any dispute concerning the permit-granting process for defence readiness projects is resolved in a timely manner. To that end, Member States should ensure that project promoters have access to simple dispute settlement procedures and that defence readiness projects are subject to urgent handling in all administrative, judicial and dispute resolution procedures relating to the projects to the extent that national law provides for such urgency procedures.
(17)eingefügt: (17) In order to provide project promoters and other investors with the security and clarity needed to increase development of defence readiness projects, Member States should ensure that the permit-granting process related to such projects does not exceed set time limits.eingefügt: Completion within those time limits should take the form of a reasoned, written decision, whether granting or refusing the relevant permit, - notified by the single point of contact to the project promoter.
(18)This Regulation is without prejudice to the obligations deriving from international law, where relevant.
(19)Since the objective of this Regulation cannot be sufficiently achieved by the Member States and can rather, by reason of the scale or effects of the action, be better achieved at Union level, the Union may adopt measures in accordance with the principle of subsidiarity as set out in Article 5 of the Treaty on the European Union. In accordance with the principle of proportionality as set out in that Article, this Regulation does not go beyond what is necessary in order to achieve that objective,
HAVE ADOPTED THIS REGULATION:
Article 1 Definitions
For the purposes of this Regulation, the following definitions shall apply:
(1)eingefügt: (1) ‘defence readiness project’ means set of activities, investments and measures gestrichen: aimedeingefügt: or gestrichen: ateingefügt: measures gestrichen: enhancingeingefügt: primarily eingefügt: intended to enhance the defence readiness of a Member State or several Member States, eingefügt: jointly, including through the development eingefügt: or modernisation of the defence industry;
(2)eingefügt: (2) ‘defence industry’ means all undertakings engaged in the development, production, and manufacture eingefügt: or supply of defence-related products as defined in Article 3(1) of Directive 2009/43/EC of the European Parliament and of the Council;eingefügt: 6 or in the provision of services that enhance the defence readiness of one or several Member States;
(3)eingefügt: (3) ‘defence readiness’ means the state of preparedness of a Member State or several Member States to eingefügt: anticipate, prevent or respond to a crisis eingefügt: as defined in Article 1, point (10) of Directive 2009/81/EC of the European Parliament and of the Council, eingefügt: 7, which relates to defence;
(4)‘middle capitalisation company’ or ‘mid-cap’ means middle capitalisation company as defined in Article 2, point (15), of Regulation (EU) 2021/697 of the European Parliament and of the Council;
(5)‘small mid-cap enterprises’ means enterprises as defined in the Annex to Commission Recommendation (EU) 2025/1099
(6)gestrichen: ‘permit-grantingeingefügt: (6) eingefügt: permit-granting process’ means a process that covers all relevant eingefügt: permissions permits, including permits eingefügt: approvals or licences necessary to build, expand, convert and operate eingefügt: or repurpose any installation, equipment or activity for manufacturing defence gestrichen: readinesseingefügt: products gestrichen: projectseingefügt: or gestrichen: andeingefügt: components gestrichen: alleingefügt: or gestrichen: theeingefügt: for gestrichen: necessaryeingefügt: other eingefügt: activities forming part of a defence readiness project together with all administrative steps from gestrichen: the acknowledgement gestrichen: that theeingefügt: of application gestrichen: is completeeingefügt: completeness to gestrichen: the notification of the final decision gestrichen: on that application by the single gestrichen: contact point gestrichen: concerned;eingefügt: of contact;
(7)‘project promoter’ means any undertaking or consortium of undertakings developing a defence readiness project;
(8)‘small and medium-sized enterprises’ or ‘SMEs’ means small and medium-sized enterprises as defined in Article 2 of the Annex to Commission Recommendation 2003/361/EC.
Article 2 Single gestrichen: pointeingefügt: points of contact
1.eingefügt: 1. By …[3 months after the date of entry into force of this Regulation], each Member State shall establish or designate one authority as single point of contact at the relevant administrative level.eingefügt: The single point of contact shall operate as a single interface for each defence readiness project.
2.eingefügt: 2. The single point of contact shall be responsible for facilitating and coordinating the permit-granting process for defence readiness projects and for providing information on streamlining the administrative processes in accordance with Article 3, including information to the project promoter on when an application is considered to be completed in accordance with Article 5(6).eingefügt: At the request of the project promoter, the single point of contact shall also provide information whether the project could be considered a defence readiness project under this Regulation, as well as information on the required documentation to be submitted as part of the final application.
3.The single point of contact established or designated pursuant to paragraph 1 shall be the sole point of contact for the project promoter in the permit-granting process for a defence readiness project. It shall notify the project promoter of the final decision in that process.
4.eingefügt: 4. Project promoters shall be allowed eingefügt: and enabled to submit any documents relevant to the permit-granting process in electronic gestrichen: form.eingefügt: form via a secure, interoperable portal. Member States shall ensure the digital exchange of documentation between the national authority, the single point of contact and the project promoters.
5.eingefügt: 5. The competent authorities shall ensure that any relevant studies carried out, or permits or authorisations issued, for a given project are taken into account and that no duplicate studies, permits or authorisations are required, unless otherwise required under Union or national law.eingefügt: The single point of contact shall ensure the coordination among the competent authorities and those authorities shall have access to all relevant documents to facilitate the fast-track procedure.
6.eingefügt: 6. Member States shall ensure that the single point of contact and all competent authorities responsible for any step along the permit-granting processes, including all procedural steps, have enough qualified staff and sufficient financial, technical and gestrichen: technologicaleingefügt: digital resources necessary, including, where appropriate, for up- skilling and re-skilling, for the effective performance of their tasks under this Regulation.
7.eingefügt: 7. The authorities involved in the permit-granting process and other authorities concerned shall specify and make available to the single point of contact concerned, the requirements and all information requested of a project promoter before the permit-granting process commences.eingefügt: Single points of contact shall also make available relevant and necessary documents of the project promoter to the authorities, where necessary in the permit-granting process.
8.eingefügt: 8. Upon request by a Member State, the Commission gestrichen: mayeingefügt: shall assist the authorities of that Member State with capacity building in support of implementation of this Regulation, notably in establishing or operating a single point of contact.eingefügt: The Commission shall treat that request as a priority and commence implementation without undue delay in cooperation with the requesting Member State. Such assistance may include targeted technical and financial support, such as through Regulation (EU) 20XX/XXXX on the European Defence Industry Programme and cohesion policy instruments, to help Member States with limited administrative capacity.
Article 3 Online accessibility of information
Member States shall provide public access to the following information on permit-granting processes relevant to defence readiness projects, online and in a centralised and easily accessible manner:eingefügt: to the extent that such publication is without prejudice to national security and with due regard to confidentiality requirements:
(a)the single points of contact referred to in Article 2(1);
(b)the permit-granting process, including information on dispute settlement concerning the permit-granting process including, where applicable, alternative dispute resolution mechanisms, if such procedures are provided for by national law;
(c)financing and investment services;
(d)eingefügt: (d) funding possibilities at Union gestrichen: oreingefügt: and Member State level;
(e)business support services, including but not limited to corporate tax declaration, local tax laws or labour law.
Article 4 Accelerating implementation
Member States shall provide administrative support for defence readiness projects located on their territory, eingefügt: to all project promoters, regardless of the Member States in which they are established, paying particular attention to SMEs and mid-caps, including small mid-cap enterprises, involved in those projects, including by providing:
(a)eingefügt: (a) assistance regarding compliance with applicable administrative and reporting obligations;eingefügt: including with Union and national health, environmental, safety, social and labour laws;
(b)assistance to project promoters to inform the public;
(c)assistance to project promoters along the permit-granting process, in particular for SMEs and small mid-cap enterprises.
Article 5 Duration of the permit-granting process
1.eingefügt: 1. The permit-granting process for defence readiness projects, including gestrichen: the grantingeingefügt: notification of the gestrichen: relevanteingefügt: outcome gestrichen: permit,eingefügt: of eingefügt: that process, shall not exceed gestrichen: [60]eingefügt: 50 gestrichen: days.eingefügt: working days from the date of the acknowledgement of the completeness of the permit-granting application by the single point of contact.
2.gestrichen: Whereeingefügt: 2. eingefügt: In exceptional cases, and without prejudice to the ability of the competent authorities to fully and comprehensively assess compliance with Union or national law, where a defence readiness project requires the construction of several facilities or gestrichen: unitseingefügt: requires gestrichen: ineingefügt: several gestrichen: oneeingefügt: phases, eingefügt: whether located on a single site, eingefügt: or across multiple sites, the project promoter and the single point of contact may gestrichen: agreeeingefügt: where gestrichen: oneingefügt: justified gestrichen: splittingeingefügt: by the gestrichen: projecteingefügt: project’s gestrichen: intoeingefügt: technical gestrichen: severaleingefügt: or gestrichen: smallereingefügt: administrative gestrichen: projectseingefügt: characteristics, eingefügt: agree to process those components as separate sub-projects for the purposes of complying with the applicable time limits.
3.eingefügt: 3. In exceptional cases, where the nature, gestrichen: complexity, location or size of the proposed defence readiness project so requires, a Member State may once extend the time limits referred to in paragraph 1 by a maximum of gestrichen: 30eingefügt: 25 eingefügt: working days before their expiry and on a case-by-case basis.
4.eingefügt: 4. Where a Member State considers that eingefügt: there is evidence that the defence readiness project eingefügt: is of exceptional complexity, raises exceptional risks for the health and safety of workers or of the general population, eingefügt: raises an exceptional risk on the environment, or where a specific national security clearance is required, and where additional time is necessary to establish that measures to address identifiable risks have been put in place, it may extend the time limits referred to in paragraph 1 by gestrichen: 60eingefügt: 50 eingefügt: working days, within gestrichen: 30eingefügt: 25 eingefügt: working days of the start of the permit-granting process.
5.In the application of paragraph 3 or 4, the single point of contact shall inform the project promoter in writing of the reasons for the extension and of the date when the final decision is expected.
6.eingefügt: 6. No later than gestrichen: 15eingefügt: 12 eingefügt: working days from the receipt of the permit-granting application, the single point of contact concerned shall acknowledge that the application is complete and whether this Regulation applies or, if the project promoter has not sent all the information required to process the application, request the project promoter to submit a complete application without undue delay, specifying which information is missing. If the submitted application is deemed to be incomplete for a second time, the single point of contact may, within gestrichen: [15]eingefügt: 12 eingefügt: working days of the second submission, make a second request for information. The single point of contact shall not request information in areas not covered in the first request for information and shall be entitled only to request further evidence to complete the identified missing information.gestrichen: The date of the acknowledgement of the completeness of the application from the single point of contact shall serve as the start of the permit-granting process for that application.
7.The time limits set in this Article for any of the permit-granting processes shall be without prejudice to any shorter time limits set by Member States
8.eingefügt: 8. Where the single point of contact does not inform the project promoter of the outcome of the permit-granting process within the time limit set out in paragraph 1 and extended, where applicable, in accordance with paragraphs 3 and 4, the permits covered by the application shall be deemed to be gestrichen: granted.eingefügt: granted, eingefügt: unless the principle of administrative tacit approval has been excluded for these types of procedures by the national legal system of the Member state concerned. The single point of contact shall gestrichen: promptlyeingefügt: within gestrichen: delivereingefügt: 10 eingefügt: days, without undue delay but not later than within 3 working days provide written confirmation to the project promoter, eingefügt: in writing or electronically indicating that the permits have been implicitly granted based on the application submitted.
Article 6 Planning
1.eingefügt: 1. National, regional and local authorities responsible for preparing plans, including zoning, spatial plans and land use plans, shall include in such plans, where appropriate, provisions for the development of defence readiness activities, projects gestrichen: aseingefügt: and gestrichen: welleingefügt: their gestrichen: aseingefügt: required gestrichen: theeingefügt: infrastructure, gestrichen: necessaryeingefügt: and eingefügt: shall also take into account security considerations, including protection against cyber and hybrid threats targeting critical defence infrastructure. To facilitate the development of defence readiness projects, Member States shall ensure that gestrichen: alleingefügt: non-confidential relevant spatial planning data is available online in accordance with Article gestrichen: 3.eingefügt: 3 as well as with applicable Union and national law.
2.Where plans include provisions for the development of defence readiness projects, and their required infrastructure, and are subject to an assessment pursuant to Directive 2001/42/EC of the European Parliament and of the Council and pursuant to Article 6 of Council Directive 92/43/EEC, those assessments shall be combined. Where applicable, the combined assessment shall also address the impact on potentially affected water bodies referred to in Directive 2000/60/EC of the European Parliament and of the Council. Where relevant, the Member States are required to assess the impacts of existing and future activities on the marine environment, including land-sea interactions, as referred to in Article 4 of Directive 2014/89/EU of the European Parliament and of the Council those impacts shall also be covered in the combined assessment. The fact that assessments are combined pursuant to this paragraph shall not affect their content or quality. The combined assessment shall be carried out within the time limits set out in this Regulation.
Article 7 Priority status of defence readiness projects
All dispute resolution procedures, litigation, appeals and judicial remedies as well as all administrative proceedings related to defence readiness projects before any national courts, tribunals, bodies or panels, including with regard to mediation or arbitration, where they exist in national law, shall be treated as urgent if and to the extent to which national law concerning relevant permit-granting processes provides for such urgency procedures and provided that the applicable rights of defence of individuals or of local communities are respected. Project promoters of defence readiness projects shall participate in such urgency procedures, where applicable.eingefügt: The competent authorities shall guarantee that accelerated judicial and administrative procedures do not undermine the right to an effective remedy.
Article 8 Applicability of UNECE Conventions
This Regulation is without prejudice, where relevant, to the obligations under the United Nations Economic Commission for Europe (UNECE) Convention on Access to Information, Public Participation in Decision-making and Access to Justice in Environmental Matters, signed at Aarhus on 25 June 1998, and under the UNECE Convention on environmental impact assessment in a transboundary context, signed at Espoo on 25 February 1991 and its Protocol on Strategic Environmental Assessment, signed in Kyiv on 21 May 2003.
Article 9
This Regulation shall enter into force on the twentieth day following that of its publication in the Official Journal of the European Union.
It shall apply only to permit applications for defence readiness projects submitted after that date.
This Regulation shall be binding in its entirety and directly applicable in all Member States.
Nicht im Text zugeordnet
Diese Änderungsanträge konnten keiner Stelle im Vorschlag zugeordnet werden und sind daher nicht darin enthalten.
Änderungsantrag 36 · keine Plenarabstimmung zugeordnet
Nach seiner Stelle im Vorschlag eingefügt.
Grund: die Stelle „Article 2 – paragraph 4 a (new)“ wurde im Vorschlag nicht gefunden. Stelle: Article 2 – paragraph 4 a (new).
Änderungsantrag 41 · keine Plenarabstimmung zugeordnet
Nach seiner Stelle im Vorschlag eingefügt.
Grund: die Stelle „Article 2 – paragraph 8 a (new)“ wurde im Vorschlag nicht gefunden. Stelle: Article 2 – paragraph 8 a (new).
Änderungsantrag 42 · keine Plenarabstimmung zugeordnet
Nach seiner Stelle im Vorschlag eingefügt.
Grund: die Stelle „Article 2 – paragraph 8 b (new)“ wurde im Vorschlag nicht gefunden. Stelle: Article 2 – paragraph 8 b (new).
Änderungsantrag 43 · keine Plenarabstimmung zugeordnet
Nach seiner Stelle im Vorschlag eingefügt.
Grund: die Stelle „Article 2 – paragraph 8 c (new)“ wurde im Vorschlag nicht gefunden. Stelle: Article 2 – paragraph 8 c (new).
Änderungsantrag 46 · keine Plenarabstimmung zugeordnet
Nach seiner Stelle im Vorschlag eingefügt.
Grund: die Stelle „Article 3 – paragraph 1 – point e a (new)“ wurde im Vorschlag nicht gefunden. Stelle: Article 3 – paragraph 1 – point e a (new).
Änderungsantrag 47 · keine Plenarabstimmung zugeordnet
Nach seiner Stelle im Vorschlag eingefügt.
Grund: die Stelle „Article 3 – paragraph 1 – point e b (new)“ wurde im Vorschlag nicht gefunden. Stelle: Article 3 – paragraph 1 – point e b (new).
Änderungsantrag 50 · keine Plenarabstimmung zugeordnet
Nach seiner Stelle im Vorschlag eingefügt.
Grund: die Stelle „Article 4 – paragraph 1 – point c a (new)“ wurde im Vorschlag nicht gefunden. Stelle: Article 4 – paragraph 1 – point c a (new).
Änderungsantrag 51 · keine Plenarabstimmung zugeordnet
Nach seiner Stelle im Vorschlag eingefügt.
Grund: die Stelle „Article 4 – paragraph 1 – point c b (new)“ wurde im Vorschlag nicht gefunden. Stelle: Article 4 – paragraph 1 – point c b (new).
Änderungsantrag 53 · keine Plenarabstimmung zugeordnet
Nach seiner Stelle im Vorschlag eingefügt.
Grund: die Stelle „Article 5 – paragraph 1 a (new)“ wurde im Vorschlag nicht gefunden. Stelle: Article 5 – paragraph 1 a (new).
Änderungsantrag 58 · keine Plenarabstimmung zugeordnet
Nach seiner Stelle im Vorschlag eingefügt.
Grund: die Stelle „Article 5 – paragraph 6 a (new)“ wurde im Vorschlag nicht gefunden. Stelle: Article 5 – paragraph 6 a (new).
Änderungsantrag 61 · keine Plenarabstimmung zugeordnet
Nach seiner Stelle im Vorschlag eingefügt.
Grund: die Stelle „Article 6 – paragraph 2 a (new)“ wurde im Vorschlag nicht gefunden. Stelle: Article 6 – paragraph 2 a (new).
Änderungsantrag 63 · keine Plenarabstimmung zugeordnet
Nach seiner Stelle im Vorschlag eingefügt.
Grund: die Stelle „Article 8 a (new)“ wurde im Vorschlag nicht gefunden. Stelle: Article 8 a (new).
Das Dokument des Parlaments in der veröffentlichten Fassung (die Änderungsanträge als Tabellen) →
Verfahrensseiten
Wie die Ausschüsse den Text behandelt und wie ihre Mitglieder darüber abgestimmt haben.
Procedure – committee asked for opinion 1 Absatz
| Title | Acceleration of permit-granting for defence readiness projects | |
| References | COM(2025)0821 – C10-0122/2025 – 2025/0172(COD) | |
| Committee(s) responsible Date announced in plenary | SEDE 8.9.2025 | IMCO 8.9.2025 |
| Opinion by Date announced in plenary | ENVI 8.9.2025 | |
| Rapporteur for the opinion Date appointed | Antonio Decaro 1.10.2025 | |
| Rule 59 – Joint committee procedure Date announced in plenary | 8.9.2025 | |
| Simplified procedure - date of decision | 23.9.2025 | |
| Date adopted | 3.12.2025 | |
| Result of final vote | +: –: 0: | 54 17 5 |
| Members present for the final vote | Grégory Allione, Pascal Arimont, Sakis Arnaoutoglou, Christophe Clergeau, Annalisa Corrado, Antonio Decaro, Viktória Ferenc, Pietro Fiocchi, Emma Fourreau, Anne-Sophie Frigout, Heléne Fritzon, Hanna Gronkiewicz-Waltz, Roman Haider, Martin Hojsík, Romana Jerković, Stefan Köhler, András Tivadar Kulja, Peter Liese, César Luena, Elżbieta Katarzyna Łukacijewska, Ignazio Roberto Marino, Dan-Ştefan Motreanu, Rasmus Nordqvist, Michele Picaro, Jessica Polfjärd, Massimiliano Salini, Silvia Sardone, Lena Schilling, Christine Schneider, Günther Sidl, Sander Smit, Susana Solís Pérez, Antonín Staněk, Ingeborg Ter Laak, Beatrice Timgren, Dimitris Tsiodras, Ana Vasconcelos, Aurelijus Veryga, Kristian Vigenin, Alexandr Vondra, Michal Wiezik, Tiemo Wölken, Anna Zalewska | |
| Substitutes present for the final vote | Michael Bloss, Biljana Borzan, Marie-Luce Brasier-Clain, Stefano Cavedagna, Susanna Ceccardi, Per Clausen, Raúl de la Hoz Quintano, Nikolas Farantouris, Sigrid Friis, Michalis Hadjipantela, Martin Häusling, Sérgio Humberto, Adam Jarubas, Pierre Jouvet, Norbert Lins, Sara Matthieu, Danuše Nerudová, Valentina Palmisano, Dennis Radtke, Elena Sancho Murillo, Antonella Sberna, Christine Singer, Anna Stürgkh, Kai Tegethoff, Ewa Zajączkowska-Hernik | |
| Members under Rule 216(7) present for the final vote | Daniel Attard, Raquel García Hermida-Van Der Walle, Mary Khan, Jaroslav Knot, Alexandra Mehnert, Matjaž Nemec, Paulius Saudargas, Volker Schnurrbusch |
Final vote by roll call by the committee asked for opinion 3 Absätze
54 · Dafür
- EVP
- Pascal Arimont, Raúl de la Hoz Quintano, Hanna Gronkiewicz-Waltz, Michalis Hadjipantela, Sérgio Humberto, Adam Jarubas, Stefan Köhler, András Tivadar Kulja, Peter Liese, Norbert Lins, Elżbieta Katarzyna Łukacijewska, Alexandra Mehnert, Dan-Ştefan Motreanu, Danuše Nerudová, Jessica Polfjärd, Dennis Radtke, Paulius Saudargas, Christine Schneider, Sander Smit, Susana Solís Pérez, Ingeborg Ter Laak, Dimitris Tsiodras
- Patrioten
- Jaroslav Knot, Antonín Staněk
- Renew
- Grégory Allione, Sigrid Friis, Raquel García Hermida-Van Der Walle, Martin Hojsík, Christine Singer, Anna Stürgkh, Ana Vasconcelos, Michal Wiezik
- S&D
- Sakis Arnaoutoglou, Daniel Attard, Biljana Borzan, Christophe Clergeau, Annalisa Corrado, Antonio Decaro, Heléne Fritzon, Romana Jerković, Pierre Jouvet, César Luena, Matjaž Nemec, Elena Sancho Murillo, Günther Sidl, Kristian Vigenin, Tiemo Wölken
- Grüne/EFA
- Michael Bloss, Martin Häusling, Ignazio Roberto Marino, Sara Matthieu, Rasmus Nordqvist, Lena Schilling, Kai Tegethoff
17 · Dagegen
- EKR
- Stefano Cavedagna, Pietro Fiocchi, Michele Picaro, Antonella Sberna, Beatrice Timgren, Aurelijus Veryga, Alexandr Vondra, Anna Zalewska
- ESN
- Mary Khan, Volker Schnurrbusch
- Patrioten
- Susanna Ceccardi, Roman Haider, Silvia Sardone
- Die Linke
- Per Clausen, Nikolas Farantouris, Emma Fourreau, Valentina Palmisano
5 · Enthalten
- ESN
- Ewa Zajączkowska-Hernik
- EVP
- Massimiliano Salini
- Patrioten
- Marie-Luce Brasier-Clain, Viktória Ferenc, Anne-Sophie Frigout
Procedure – committee responsible 1 Absatz
| Title | Acceleration of permit-granting for defence readiness projects | |
| References | COM(2025)0821 – C10-0122/2025 – 2025/0172(COD) | |
| Date submitted to Parliament | 18.6.2025 | |
| Committee(s) responsible Date announced in plenary | SEDE 8.9.2025 | IMCO 8.9.2025 |
| Committees asked for opinions Date announced in plenary | ENVI 8.9.2025 | ITRE 8.9.2025 |
| Not delivering opinions Date of decision | ITRE 23.9.2025 | |
| Rapporteurs Date appointed | Lucia Yar 3.9.2025 | Henrik Dahl 3.9.2025 |
| Rule 59 – Joint committee procedure Date announced in plenary | 8.9.2025 | |
| Discussed in committee | 10.11.2025 | |
| Date adopted | 15.12.2025 | |
| Result of final vote | +: –: 0: | 62 6 11 |
| Members present for the final vote | Peter Agius, Pablo Arias Echeverría, Petras Auštrevičius, Jeannette Baljeu, Katarina Barley, Arno Bausemer, Biljana Borzan, Marc Botenga, Stefano Cavedagna, David Cormand, Tobias Cremer, Henrik Dahl, Salvatore De Meo, Adnan Dibrani, Elisabeth Dieringer, Elio Di Rupo, Regina Doherty, Christian Doleschal, Klara Dostalova, Michał Dworczyk, Kamila Gasiuk-Pihowicz, Raphaël Glucksmann, Christophe Gomart, Sandro Gozi, Maria Grapini, Maria Guzenina, György Hölvényi, Arba Kokalari, Katrin Langensiepen, Nathalie Loiseau, Javi López, Pierfrancesco Maran, Costas Mavrides, Vangelis Meimarakis, Ana Catarina Mendes, Sven Mikser, Nikola Minchev, Piotr Müller, Denis Nesci, Hans Neuhoff, Hannah Neumann, Cynthia Ní Mhurchú, Andrey Novakov, Kostas Papadakis, Nicolás Pascual de la Parte, Jaroslava Pokorná Jermanová, Reinis Pozņaks, Marjan Šarec, Christel Schaldemose, Tomislav Sokol, Mārtiņš Staķis, Marie-Agnes Strack-Zimmermann, Michał Szczerba, Riho Terras, Pierre-Romain Thionnet, Pekka Toveri, Dimitris Tsiodras, Adina Vălean, Reinier Van Lanschot, Roberto Vannacci, Kim Van Sparrentak, Alexandr Vondra, Lucia Yar | |
| Substitutes present for the final vote | José Cepeda, Gheorghe Falcă, Michael Gahler, Rasa Juknevičienė, Alice Kuhnke, Gaetano Pedulla’, Hélder Sousa Silva, Matej Tonin, Kristian Vigenin, Tomáš Zdechovský | |
| Members under Rule 216(7) present for the final vote | Dan Barna, Alexander Jungbluth, Moritz Körner, Lukas Mandl, Maria Noichl, Annamária Vicsek | |
| Date tabled | 18.12.2025 |
Final vote by roll call by the committee responsible 3 Absätze
62 · Dafür
- EKR
- Stefano Cavedagna, Michał Dworczyk, Piotr Müller, Denis Nesci, Reinis Pozņaks, Alexandr Vondra
- EVP
- Peter Agius, Pablo Arias Echeverría, Henrik Dahl, Salvatore De Meo, Regina Doherty, Christian Doleschal, Gheorghe Falcă, Michael Gahler, Kamila Gasiuk-Pihowicz, Christophe Gomart, Rasa Juknevičienė, Arba Kokalari, Lukas Mandl, Vangelis Meimarakis, Andrey Novakov, Nicolás Pascual de la Parte, Tomislav Sokol, Hélder Sousa Silva, Michał Szczerba, Riho Terras, Matej Tonin, Pekka Toveri, Dimitris Tsiodras, Adina Vălean, Tomáš Zdechovský
- Patrioten
- Klara Dostalova, Jaroslava Pokorná Jermanová, Pierre-Romain Thionnet
- Renew
- Petras Auštrevičius, Jeannette Baljeu, Dan Barna, Sandro Gozi, Moritz Körner, Nathalie Loiseau, Nikola Minchev, Cynthia Ní Mhurchú, Marjan Šarec, Marie-Agnes Strack-Zimmermann, Lucia Yar
- S&D
- Katarina Barley, Biljana Borzan, José Cepeda, Tobias Cremer, Adnan Dibrani, Elio Di Rupo, Raphaël Glucksmann, Maria Grapini, Maria Guzenina, Javi López, Pierfrancesco Maran, Costas Mavrides, Ana Catarina Mendes, Sven Mikser, Maria Noichl, Christel Schaldemose, Kristian Vigenin
6 · Dagegen
- ESN
- Arno Bausemer, Alexander Jungbluth, Hans Neuhoff
- fraktionslos
- Kostas Papadakis
- Die Linke
- Marc Botenga, Gaetano Pedulla'
11 · Enthalten