amendment list, 18 November 2026
Speeding-up environmental assessments (Omnibus VIII on environmental legislation)
Report A-10-2026-0290-AM-115-117 · (COM(2025)0984 – C10-0337/2025 – 2025/0391(COD))
Full text
This is Parliament’s document as it publishes it: 3 amendments, each as a table with the wording it changes on the left and Parliament’s wording on the right. It has no running text — Parliament publishes no consolidated version. For the whole proposal with these amendments written in, read the text as amended.
Text 35 paragraphs
18.11.2026 A10-0290/115
Amendment 115
Mathilde Androuët, Valérie Deloge, Jorge Buxadé Villalba, Anne-Sophie Frigout, Kateřina Konečná, Antonín Staněk
on behalf of the PfE Group
Report A10-0290/2026
Emma Ytterell
(COM(2025)0984 – C10-0337/2025 – 2025/0391(COD))
Proposal for a regulation
Article 5 – paragraph 2 a (new)
| Text proposed by the Commission | Amendment |
|---|---|
| 2a. The maintenance, cleaning and clearing of riverbeds, ravines, drainage channels, irrigation channels and existing flood defence works, including dredging, desilting, removal of debris and sediment, restoration of water flow and reinforcement of existing protective infrastructure as well as the management of vegetation and forest fuel for the prevention of wildfires, including brush clearing, removal of deadwood, controlled vegetation management and the creation and maintenance of firebreaks which restore or preserve theexisting functionality, safety or resilience of the land or infrastructure shall not constitute projects or changes to projects within the meaning of Directive 2011/92/EU and shall not be subject to screening or an environmental impact assessment. |
Or. en
18.11.2026 A10-0290/116
Read the rest (23 paragraphs)
Amendment 116
Mathilde Androuët, Valérie Deloge, Jorge Buxadé Villalba, Anne-Sophie Frigout, Kateřina Konečná, Antonín Staněk
on behalf of the PfE Group
Report A10-0290/2026
Emma Ytterell
Speeding-up environmental assessments (Omnibus VIII on environmental legislation)
(COM(2025)0984 – C10-0337/2025 – 2025/0391(COD))
Proposal for a regulation
Article 7 – paragraph 1 a (new)
| Text proposed by the Commission | Amendment |
|---|---|
| 1a. By way of derogation from paragraph 1, for projects for the construction or renovation of residential buildings, water infrastructure projects contributing to water security, drought resilience or flood protection, including water storage facilities, reservoirs, dams, drainage systems and flood defence infrastructure, and projects for the modernisation of agricultural and livestock holdings and of irrigation infrastructure, including water storage, water reuse and on-farm water management systems, Member States shall ensure that: | |
| (a) the screening is carried out within a maximum of 30 days from the date on which the developer has submitted all information required; where the competent authority has not taken a screening decision within that period, the project shall be deemed not to require an environmental impact assessment, unless the project may pose a demonstrable and significant risk to the safety of residents in its vicinity; | |
| (b) where an environmental impact assessment is required, the complete environmental assessment, excluding the preparation of the environmental impact assessment report by the developer, does not exceed 90 days. |
Or. en
18.11.2026 A10-0290/117
Amendment 117
Mathilde Androuët, Valérie Deloge, Kateřina Konečná, Antonín Staněk
on behalf of the PfE Group
Report A10-0290/2026
Emma Ytterell
Speeding-up environmental assessments (Omnibus VIII on environmental legislation)
(COM(2025)0984 – C10-0337/2025 – 2025/0391(COD))
Proposal for a regulation
Article 8 – paragraph 1
| Text proposed by the Commission | Amendment |
|---|---|
| 1. When the implementation of plans or when the construction, operation or decommissioning of projects result in the occasional killing or disturbance of birds protected under Directive 2009/147/EC or other species protected under Directive 92/43/EEC, such killing or disturbance of protected species shall not be considered to be deliberate within the meaning of Article 5 of Directive 2009/147/EC and Article 12(1) of Directive 92/43/EEC, provided that the plan or project has adopted appropriate and proportionate mitigation measures and considering the best available technologies to avoid such killing and to prevent disturbance. | 1. Where the plans, projects, works or recurring activities referred to in the first subparagraph result in the deterioration or destruction of breeding sites or resting places of species protected under Directive 92/43/EEC, this shall not be considered as prohibited within the meaning of Article 12(1), point (d), of that Directive, provided that the relevant Member State authority has determined that the plan, project, works or recurring activity includes appropriate and proportionate measures, which may be defined under specific national or regional regimes, to avoid such deterioration or destruction. |
Or. en