This is Parliament’s document as it publishes it: 5 amendments, each as a table with the wording it changes on the left and Parliament’s wording on the right. It has no running text — Parliament publishes no consolidated version. For the whole proposal with these amendments written in, read the text as amended.
Jump to an amendment (5)
Text 59 paragraphs
18.11.2026 A10-0290/98
Amendment 98
Emma Fourreau
on behalf of The Left Group
Report A10-0290/2026
Emma Ytterell
(COM(2025)0984 – C10-0337/2025 – 2025/0391(COD))
Proposal for a regulation
Article 5
| Text proposed by the Commission | Amendment |
|---|---|
| Article 5 | deleted |
| Changes to projects | |
| 1. Changes or extensions of projects, such as repurposing of pipelines or of industrial sites, and extension of their operation period and modifications to ensure decarbonisation, shall only be subject to screening by the competent authorities in order to determine if they are likely to have significant effects on the environment. Those changes or extensions shall be subject to an environmental assessment only where they involve major works that represent risks that are similar to or greater than, in terms of their effects on the environment, to those posed by the original project. | |
| 2. For changes or extensions of projects which are likely to have significant effects on the environment in another Member State or where a Member State that is likely to be significantly affected so requests, the Member State in whose territory the project is intended to be carried out shall ensure that Article 7 of Directive 2011/92/EU is applied. |
Or. fr
18.11.2026 A10-0290/99
Read the rest (47 paragraphs)
Amendment 99
Emma Fourreau
on behalf of The Left Group
Report A10-0290/2026
Emma Ytterell
Speeding up environmental assessments (Omnibus VIII on environmental legislation)
(COM(2025)0984 – C10-0337/2025 – 2025/0391(COD))
Proposal for a regulation
Article 7 – paragraph 5 a (new)
| Text proposed by the Commission | Amendment |
|---|---|
| 5a. Competent authorities may decide to adapt the time limits provided for in this Article on a case-by-case basis where they consider it necessary to ensure the integrity and completeness of the environmental assessment. |
Or. fr
18.11.2026 A10-0290/100
Amendment 100
Emma Fourreau
on behalf of The Left Group
Report A10-0290/2026
Emma Ytterell
Speeding up environmental assessments (Omnibus VIII on environmental legislation)
(COM(2025)0984 – C10-0337/2025 – 2025/0391(COD))
Proposal for a regulation
Article 8
| Text proposed by the Commission | Amendment |
|---|---|
| Article 8 | deleted |
| Protected species | |
| 1. When the implementation of plans or when the construction, operation or decommissioning of projects result in the occasional killing or disturbance of birds protected under Directive 2009/147/EC or other species protected under Directive 92/43/EEC, such killing or disturbance of protected species shall not be considered to be deliberate within the meaning of Article 5 of Directive 2009/147/EC and Article 12(1) of Directive 92/43/EEC, provided that the plan or project has adopted appropriate and proportionate mitigation measures and considering the best available technologies to avoid such killing and to prevent disturbance. | |
| 2. When assessing whether those mitigation measures are appropriate and proportionate to comply with Article 5 of the Birds Directive and Article 12(1) of the Habitats Directive, the competent authority shall take into account whether they ensure that significant adverse impacts on the population of the species concerned is avoided, despite the possible existence of negative impacts on individual specimens of those species. Member States shall ensure that those measures are applied and their effectiveness is monitored and that, in the light of the information gathered, further measures are taken as required to ensure that there are no significant adverse impacts on the population of the species concerned. |
Or. fr
18.11.2026 A10-0290/101
Amendment 101
Emma Fourreau
on behalf of The Left Group
Report A10-0290/2026
Emma Ytterell
Speeding up environmental assessments (Omnibus VIII on environmental legislation)
(COM(2025)0984 – C10-0337/2025 – 2025/0391(COD))
Proposal for a regulation
Article 14
| Text proposed by the Commission | Amendment |
|---|---|
| Article 14 | deleted |
| Toolbox for strategic sectors or categories | |
| 1. | |
| The provisions set out in the Annex shall apply where existing sectorial Union legislation defines strategic sectors or categories of strategic projects and aims to speed up permitting, provided that those projects contribute to resilience and decarbonisation or resource efficiency. | |
| The Commission is empowered to adopt an implementing act identifying strategic projects for the construction and renovation of residential affordable or social buildings, as well as the necessary infrastructure that directly serves those buildings. The provisions set out in the Annex shall apply to those projects. | |
| 2. The provisions set out in the Annex shall also apply to strategic sectors or categories of projects defined in future Union legislation which refers to this Regulation, provided that those projects contribute to resilience and decarbonisation or resource efficiency. |
Or. fr
18.11.2026 A10-0290/102
Amendment 102
Emma Fourreau
on behalf of The Left Group
Report A10-0290/2026
Emma Ytterell
Speeding up environmental assessments (Omnibus VIII on environmental legislation)
(COM(2025)0984 – C10-0337/2025 – 2025/0391(COD))
Proposal for a regulation
Annex 1
| Text proposed by the Commission | Amendment |
|---|---|
| [...] | deleted |
Or. fr