This is Parliament’s document as it publishes it: 7 amendments, each as a table with the wording it changes on the left and Parliament’s wording on the right, and under each what Parliament decided on it. It has no running text — Parliament publishes no consolidated version. For the whole proposal with these amendments written in, read the text as amended.
Jump to an amendment (7)
Text 83 paragraphs
18.11.2026 A10-0290/91
Amendment 91
Emma Fourreau
on behalf of The Left Group
Report A10-0290/2026
Emma Ytterell
(COM(2025)0984 – C10-0337/2025 – 2025/0391(COD))
Proposal for a regulation
Recital -1
| Text proposed by the Commission | Amendment |
|---|---|
| (-1) Environmental assessments these days are often inadequate, or even non-existent for some projects, and lead to legal challenges that result in the projects being cancelled. Work on cancelled projects has sometimes already begun, causing irreversible damage to ecosystems. Environmental assessments must therefore be strengthened, not weakened, in order to prevent biodiversity destruction caused by projects that are ultimately cancelled by the courts. |
Not in the text — rejected by show of hands
Rejected show of hands
Or. fr
18.11.2026 A10-0290/92
Read the rest (71 paragraphs)
Amendment 92
Emma Fourreau
on behalf of The Left Group
Report A10-0290/2026
Emma Ytterell
Speeding up environmental assessments (Omnibus VIII on environmental legislation)
(COM(2025)0984 – C10-0337/2025 – 2025/0391(COD))
Proposal for a regulation
Recital -1 a (new)
| Text proposed by the Commission | Amendment |
|---|---|
| (-1a) Civic participation is a crucial factor in the green transition, and no project should be allowed to go ahead without the public being consulted and involved through democratic processes. |
Not in the text — rejected by show of hands
Rejected show of hands
Or. fr
18.11.2026 A10-0290/93
Amendment 93
Emma Fourreau
on behalf of The Left Group
Report A10-0290/2026
Emma Ytterell
Speeding up environmental assessments (Omnibus VIII on environmental legislation)
(COM(2025)0984 – C10-0337/2025 – 2025/0391(COD))
Proposal for a regulation
Recital -1 b (new)
| Text proposed by the Commission | Amendment |
|---|---|
| (-1b) The sixth mass extinction is mainly the result of human activity, and projects must be redesigned to reduce their impact on ecosystems, otherwise questions must be raised about their usefulness. |
Not in the text — rejected by show of hands
Rejected show of hands
Or. fr
18.11.2026 A10-0290/94
Amendment 94
Emma Fourreau
on behalf of The Left Group
Report A10-0290/2026
Emma Ytterell
Speeding up environmental assessments (Omnibus VIII on environmental legislation)
(COM(2025)0984 – C10-0337/2025 – 2025/0391(COD))
Proposal for a regulation
Recital 1 a (new)
| Text proposed by the Commission | Amendment |
|---|---|
| (1a) The intensification of heatwaves and the periods of extreme heat affecting the European Union are the result of a lack of environmental preparedness, and no new project should be authorised without the challenges of adapting to climate change having been taken into account. |
Not in the text — rejected by show of hands
Rejected show of hands
Or. fr
18.11.2026 A10-0290/95
Amendment 95
Emma Fourreau
on behalf of The Left Group
Report A10-0290/2026
Emma Ytterell
Speeding up environmental assessments (Omnibus VIII on environmental legislation)
(COM(2025)0984 – C10-0337/2025 – 2025/0391(COD))
Proposal for a regulation
Article 4 – paragraph 1 – subparagraph 3
| Text proposed by the Commission | Amendment |
|---|---|
| Under the joint procedure referred to in the first subparagraph, a competent authority shall provide for a single assessment of the environmental impact of a particular plan, programme or project required by the relevant Directives. | Under the joint procedure referred to in the first subparagraph, a competent authority may provide for a single assessment of the environmental impact of a particular plan, programme or project required by the relevant Directives. |
Not in the text — rejected by show of hands
Rejected show of hands
Or. fr
18.11.2026 A10-0290/96
Amendment 96
Emma Fourreau
on behalf of The Left Group
Report A10-0290/2026
Emma Ytterell
Speeding up environmental assessments (Omnibus VIII on environmental legislation)
(COM(2025)0984 – C10-0337/2025 – 2025/0391(COD))
Proposal for a regulation
Article 4 – paragraph 3
| Text proposed by the Commission | Amendment |
|---|---|
| 3. In the case of plans, programmes or projects for which the obligation to carry out assessments of the effects on the environment arises simultaneously from two or more of the Directives referred to in Article 1(1), Member States shall issue one single opinion on the scope and level of detail of the information to be included in the environmental assessment report. | 3. In the case of plans, programmes or projects for which the obligation to carry out assessments of the effects on the environment may arise simultaneously from two or more of the Directives referred to in Article 1(1), Member States shall issue one single opinion on the scope and level of detail of the information to be included in the environmental assessment report. |
Not in the text — rejected by show of hands
Rejected show of hands
Or. fr
18.11.2026 A10-0290/97
Amendment 97
Emma Fourreau
on behalf of The Left Group
Report A10-0290/2026
Emma Ytterell
Speeding up environmental assessments (Omnibus VIII on environmental legislation)
(COM(2025)0984 – C10-0337/2025 – 2025/0391(COD))
Proposal for a regulation
Article 4 – paragraph 4
| Text proposed by the Commission | Amendment |
|---|---|
| 4. Competent authorities shall consult the public concerned by the environmental decision-making procedure relating to a plan, programme or project subject to an assessment in accordance with paragraph 1 at the same time as they consult the authorities likely to be concerned by that plan, programme or project by reason of their specific environmental responsibilities or local and regional competences referred to in Article 6(2) of Directive 2001/42/EC and Article 6(1) of Directive 2011/92/EU. | 4. Where appropriate, competent authorities shall consult the public concerned by the environmental decision-making procedure relating to a plan, programme or project subject to an assessment in accordance with paragraph 1 at the same time as they consult the authorities likely to be concerned by that plan, programme or project by reason of their specific environmental responsibilities or local and regional competences referred to in Article 6(2) of Directive 2001/42/EC and Article 6(1) of Directive 2011/92/EU. |
Not in the text — rejected by show of hands
Rejected show of hands
Or. fr